=Fri Nov 28, 2025=
Morning: 10:00am-1:00pm
* Removed unnecessary electric box from old position
* Installed additional wall studs in bathroom 1 and 2 to mount future divider walls/pocket doors
* Helped Ethan with some electric work
Afternoon: 2:55pm-5:20pm
* Helped James move heavy items out of storage
=Wed Nov 26, 2025=
Afternoon: 2:30pm-3:30pm
* Cleaned out leftover insulation & tools to prepare for drywall installation
* Started preparing installation of Minisplit heat pump
=Tue Nov 25, 2025=
Morning: 10:20am-12:05pm
* Installed ceiling supports for drywall on short walls
Afternoon: 1:25pm-4:30pm
* Installed ceiling supports for drywall on interior walls
* Finished all the insulation we aren't blocked on (by minisplit, breaker panel install)
* Installed vanity light blocking
=Mon Nov 24, 2025=
Morning: 10:30am-1:25pm
* Installed some electric boxes in ceiling
* Installed ceiling supports for drywall on short walls
Afternoon: 2:05pm-5:30pm
* Finished bio digester cabin roof
* Finished ceiling insulation
* Continued on wall insulation
=Fri Nov 21, 2025=
Morning: 10:15am-12:20pm
* Tried settling bio digester cabin walls with ratchet straps
* Installed remaining ceiling insulation
Afternoon: 1:15pm-5pm
* Installed wall insulation
=Thu Nov 20, 2025=
Morning: 10:50am-1:00pm
* Built & installed roof gutter mesh lath
Afternoon: 2:00pm-5:20pm
* Continued bio digester cabin build
=Wed Nov 19, 2025=
Morning: 10:00am-1:18pm
* Built bio digester cabin foundation
* Transported tools to FeF
Afternoon: 2:35pm-6:00pm
* Put up bio digester cabin (70% complete?)
=Tue Nov 18, 2025=
Morning: 10:00am-12:05pm
* Finished shingle install! Hallelujah!
* Cleaned up & organized build site
Afternoon: 1:30pm-5:15pm
* Installed drip cap L-bracket on front veranda
* Installed 1x8 white trim over front veranda
* Installed vertical 1x6 white trim on front veranda sides
=Mon Nov 17, 2025=
Morning: 10:00am-1:20pm
* Cut & installed remaining T1-11 on front porch inside walls
[[File:T1 11.jpg|thumb|T1 11]]
* Replaced split front porch plank
[[File:Plank.jpg|thumb|Plank replaced]]
Afternoon: 2:35pm-5:20pm
* Trimmed shingles to fit cedar trim
* Installed cedar shingle trim
[[File:Shingle trim.jpg|thumb|Shingle cedar trim]]
* Installed even more shingles
=Fri Nov 14, 2025=
Morning: 10:10pm-1:20pm
* Installed more shingles (1 week of shingles now!)
Afternoon: 2:25pm-5:50pm
* Installed even more shingles
* Installed missing rear porch plank
[[File:Shingles5.jpg|thumb|Shingles]]
=Thu Nov 13, 2025=
Morning: 10:10am-1:20pm
* Installed more shingles
[[File:Shingles4.jpg|thumb|Shingles]]
Afternoon: 2:30pm-5:40pm
* Installed yet more shingles
* Added some more screws to sheet metal siding
* Took T1-11 siding off back porch walls (exterior) to make room for treated plywood
* Installed window trim spacer
* Started cutting J-channel for window
Evening: 8:15pm-11:10pm
* Drove to Menards to pick up materials
=Wed Nov 12, 2025=
Morning: 10:00am-12:00pm
* Drove to FeF to get more materials (gravel, trim boards, interior doors)
Afternoon: 12:00pm-5:40pm
* Spread more gravel on roof
* Installed more shingles
=Tue Nov 11, 2025=
Morning: -
Afternoon: 12:45pm-5:45pm
* Installed some more shingles
* Spread some more gravel on the roof
=Mon Nov 10, 2025=
Morning: 10:20am-1:40pm
* Installed front porch shingles
Afternoon: 2:55pm-5:15pm
* Continued installing front porch shingles (1/3 done)
[[File:Shingles1.jpg|thumb|Shingles]]
* Spread gravel on roof (1/2 done)
[[File:Gravel.jpg|thumb|Gravel]]
=Fri Nov 7, 2025=
Morning: -
Afternoon: 1:00pm-5:50pm
* Installed back & front porch trim spacers
[[File:Front deck trim spacers.jpg|thumb|Front deck trim spacers]]
* Started installing cedar shingles on front porch wall
=Thu Nov 6, 2025=
Morning: 10:20am-1:10pm
* Installed 6x6 posts on front porch
[[File:Front deck.jpg|thumb|Front deck posts]]
Afternoon: 2:30pm-5:50pm
* Installed sheet metal roofing on front porch
[[File:Front deck roof metal.jpg|thumb|Front deck roof metal]]
------
=Wed Nov 5, 2025=
Morning: 10:00am-12:45pm
* Carried gravel bags onto roof
* Shimmed & squared french door
[[File:French door shim.jpg|thumb|French door shim]]
Lunch: 12:45pm-2:50pm
Afternoon: 2:50pm-5:50pm
* Replaced front porch boards under french door
* Lifted up all 3 front porch roof modules
* Fixed rear of all 3 front porch roof modules to house wall
[[File:Front deck roof3.jpg|thumb|Front deck roof modules installed]]
=Tue Nov 4, 2025=
Morning: 10:30am-12:40pm
* Added more screws to back porch sheet metal roof, was flapping in the wind
* Started on french door installation
* Installed tar flashing tape in french door frame
[[File:Door flashing tape.jpg|thumb|French door tar flashing tape]]
Lunch: 12:40pm-1:35pm
Afternoon: 1:35pm-5:05pm
* Installed french door
[[File:French door deck.jpg|thumb|French door installed]]
* Leveled part of front porch a bit better to fit front porch wall
* Installed second front porch wall
* Carried all 3 front porch roof modules to front of building for installation
=Mon Nov 3, 2025=
Morning: 10:25am-2:40pm
* Installed back porch walls
* Built back porch 2nd roof module
Lunch: 2:40pm-3:55pm
Afternoon: 3:55pm-6:00pm
* Installed back porch roof modules
* Installed back porch 4x4 post
* Installed back porch metal roofing
[[File:Rear deck roof metal.jpg|thumb|Rear deck]]
=Sat Nov 1, 2025=
Morning: 10:00am-12:00pm
* Installed flashing tape on both sliding doors
[[File:Sliding doors flashing.jpg|thumb|Sliding door flashing tape]]
* Built back veranda walls
[[File:Back porch wall frames.jpg|thumb|Back veranda wall frames]]
[[File:Back porch wall siding.jpg|thumb|Back veranda with wall siding installed]]
Lunch: -
Afternoon: 12:00pm-4:30pm
* Leveled, positioned, and fixed front porch beneath sliding doors
[[File:Back porch installed.jpg|thumb|Back veranda installed]]
=Fri Oct 31, 2025=
Morning: 10:25am-2pm
* Finished 2nd window installation
[[File:Window tar seal.jpg|thumb|Window sealed with tar tape]]
* Build back veranda frame and installed planks
[[File:Back porch frame.jpg|thumb|Back porch frame]]
[[File:Back porch planks.jpg|thumb|Back veranda frame with planks installed]]
Lunch: 2pm-3:35pm
Afternoon: 3:35pm-7pm
* Finished back veranda deck
* Started back veranda wall frames
* Screwed in 2nd rear veranda door frame
=Thu Oct 30, 2025=
Morning: 10:00am-12:00pm
* Trimmed PV runners
[[File:Flush runners.jpg|thumb|PV runners flush with cap]]
* Fixed up PV runner cap 2x4 on the 3rd module
* Folded up roof membrane at the south side to fit with PV runner cap 2x4s
[[File:End cap wrap.jpg|thumb|Wrapped & taped up end caps between modules]]
* Installed some 1x6 roof trim
[[File:Trim boards.jpg|thumb|1x6 trim board on roof]]
Lunch: -
Afternoon: 12:00pm-6:45pm
* Installed siding
[[File:Siding 3.jpg|thumb|Metal siding]]
* Cut opening for east side windows
[[File:Window holes.jpg|thumb|Cut window holes]]
* Installed flashing tar tape on both window frames
[[File:Window flashing tape.jpg|thumb|Window flashing tape]]
* Installed first window
[[File:Window installed.jpg|thumb]]
* Started installation of second window
=Wed Oct 29, 2025=
Morning: 10:10am-12:15pm
* Installed PV panels
[[File:Solar1.jpg|thumb|Solar panels closeup]]
[[File:Solar2.jpg|thumb|First row of solar panels installed]]
Lunch: 12:15pm-1:40pm
Afternoon: 1:40pm-7pm
* Finished installing PV panels
[[File:Solar3.jpg|thumb|Solar panel installation nearly complete]]
[[File:Solar4.jpg|thumb|Solar panel installation complete]]
* Trimmed roof membrane on east side of building to fit trim boards
* Started installing trim boards on roof


=Tue Oct 28, 2025=
=Tue Oct 28, 2025=

Latest revision as of 05:33, 29 November 2025

Build Pictures

Time Log

Write down morning work done, lunch time, and afternoon work done.

Fri Nov 28, 2025

Morning: 10:00am-1:00pm

  • Removed unnecessary electric box from old position
  • Installed additional wall studs in bathroom 1 and 2 to mount future divider walls/pocket doors
  • Helped Ethan with some electric work

Afternoon: 2:55pm-5:20pm

  • Helped James move heavy items out of storage

Wed Nov 26, 2025

Afternoon: 2:30pm-3:30pm

  • Cleaned out leftover insulation & tools to prepare for drywall installation
  • Started preparing installation of Minisplit heat pump

Tue Nov 25, 2025

Morning: 10:20am-12:05pm

  • Installed ceiling supports for drywall on short walls

Afternoon: 1:25pm-4:30pm

  • Installed ceiling supports for drywall on interior walls
  • Finished all the insulation we aren't blocked on (by minisplit, breaker panel install)
  • Installed vanity light blocking

Mon Nov 24, 2025

Morning: 10:30am-1:25pm

  • Installed some electric boxes in ceiling
  • Installed ceiling supports for drywall on short walls

Afternoon: 2:05pm-5:30pm

  • Finished bio digester cabin roof
  • Finished ceiling insulation
  • Continued on wall insulation

Fri Nov 21, 2025

Morning: 10:15am-12:20pm

  • Tried settling bio digester cabin walls with ratchet straps
  • Installed remaining ceiling insulation

Afternoon: 1:15pm-5pm

  • Installed wall insulation

Thu Nov 20, 2025

Morning: 10:50am-1:00pm

  • Built & installed roof gutter mesh lath

Afternoon: 2:00pm-5:20pm

  • Continued bio digester cabin build

Wed Nov 19, 2025

Morning: 10:00am-1:18pm

  • Built bio digester cabin foundation
  • Transported tools to FeF

Afternoon: 2:35pm-6:00pm

  • Put up bio digester cabin (70% complete?)

Tue Nov 18, 2025

Morning: 10:00am-12:05pm

  • Finished shingle install! Hallelujah!
  • Cleaned up & organized build site

Afternoon: 1:30pm-5:15pm

  • Installed drip cap L-bracket on front veranda
  • Installed 1x8 white trim over front veranda
  • Installed vertical 1x6 white trim on front veranda sides

Mon Nov 17, 2025

Morning: 10:00am-1:20pm

  • Cut & installed remaining T1-11 on front porch inside walls
T1 11
  • Replaced split front porch plank
Plank replaced

Afternoon: 2:35pm-5:20pm

  • Trimmed shingles to fit cedar trim
  • Installed cedar shingle trim
Shingle cedar trim
  • Installed even more shingles

Fri Nov 14, 2025

Morning: 10:10pm-1:20pm

  • Installed more shingles (1 week of shingles now!)

Afternoon: 2:25pm-5:50pm

  • Installed even more shingles
  • Installed missing rear porch plank
Shingles

Thu Nov 13, 2025

Morning: 10:10am-1:20pm

  • Installed more shingles
Shingles

Afternoon: 2:30pm-5:40pm

  • Installed yet more shingles
  • Added some more screws to sheet metal siding
  • Took T1-11 siding off back porch walls (exterior) to make room for treated plywood
  • Installed window trim spacer
  • Started cutting J-channel for window

Evening: 8:15pm-11:10pm

  • Drove to Menards to pick up materials

Wed Nov 12, 2025

Morning: 10:00am-12:00pm

  • Drove to FeF to get more materials (gravel, trim boards, interior doors)

Afternoon: 12:00pm-5:40pm

  • Spread more gravel on roof
  • Installed more shingles

Tue Nov 11, 2025

Morning: -

Afternoon: 12:45pm-5:45pm

  • Installed some more shingles
  • Spread some more gravel on the roof

Mon Nov 10, 2025

Morning: 10:20am-1:40pm

  • Installed front porch shingles

Afternoon: 2:55pm-5:15pm

  • Continued installing front porch shingles (1/3 done)
Shingles
  • Spread gravel on roof (1/2 done)
Gravel

Fri Nov 7, 2025

Morning: -

Afternoon: 1:00pm-5:50pm

  • Installed back & front porch trim spacers
Front deck trim spacers
  • Started installing cedar shingles on front porch wall

Thu Nov 6, 2025

Morning: 10:20am-1:10pm

  • Installed 6x6 posts on front porch
Front deck posts

Afternoon: 2:30pm-5:50pm

  • Installed sheet metal roofing on front porch
Front deck roof metal

Wed Nov 5, 2025

Morning: 10:00am-12:45pm

  • Carried gravel bags onto roof
  • Shimmed & squared french door
French door shim

Lunch: 12:45pm-2:50pm

Afternoon: 2:50pm-5:50pm

  • Replaced front porch boards under french door
  • Lifted up all 3 front porch roof modules
  • Fixed rear of all 3 front porch roof modules to house wall
Front deck roof modules installed

Tue Nov 4, 2025

Morning: 10:30am-12:40pm

  • Added more screws to back porch sheet metal roof, was flapping in the wind
  • Started on french door installation
  • Installed tar flashing tape in french door frame
French door tar flashing tape

Lunch: 12:40pm-1:35pm

Afternoon: 1:35pm-5:05pm

  • Installed french door
French door installed
  • Leveled part of front porch a bit better to fit front porch wall
  • Installed second front porch wall
  • Carried all 3 front porch roof modules to front of building for installation

Mon Nov 3, 2025

Morning: 10:25am-2:40pm

  • Installed back porch walls
  • Built back porch 2nd roof module

Lunch: 2:40pm-3:55pm

Afternoon: 3:55pm-6:00pm

  • Installed back porch roof modules
  • Installed back porch 4x4 post
  • Installed back porch metal roofing
Rear deck

Sat Nov 1, 2025

Morning: 10:00am-12:00pm

  • Installed flashing tape on both sliding doors
Sliding door flashing tape
  • Built back veranda walls
Back veranda wall frames
Back veranda with wall siding installed

Lunch: -

Afternoon: 12:00pm-4:30pm

  • Leveled, positioned, and fixed front porch beneath sliding doors
Back veranda installed

Fri Oct 31, 2025

Morning: 10:25am-2pm

  • Finished 2nd window installation
Window sealed with tar tape


  • Build back veranda frame and installed planks
Back porch frame
Back veranda frame with planks installed

Lunch: 2pm-3:35pm

Afternoon: 3:35pm-7pm

  • Finished back veranda deck
  • Started back veranda wall frames
  • Screwed in 2nd rear veranda door frame

Thu Oct 30, 2025

Morning: 10:00am-12:00pm

  • Trimmed PV runners
PV runners flush with cap
  • Fixed up PV runner cap 2x4 on the 3rd module
  • Folded up roof membrane at the south side to fit with PV runner cap 2x4s
Wrapped & taped up end caps between modules
  • Installed some 1x6 roof trim
1x6 trim board on roof

Lunch: -

Afternoon: 12:00pm-6:45pm

  • Installed siding
Metal siding
  • Cut opening for east side windows
Cut window holes
  • Installed flashing tar tape on both window frames
Window flashing tape
  • Installed first window
Window installed.jpg
  • Started installation of second window

Wed Oct 29, 2025

Morning: 10:10am-12:15pm

  • Installed PV panels
Solar panels closeup
First row of solar panels installed

Lunch: 12:15pm-1:40pm

Afternoon: 1:40pm-7pm

  • Finished installing PV panels
Solar panel installation nearly complete
Solar panel installation complete
  • Trimmed roof membrane on east side of building to fit trim boards
  • Started installing trim boards on roof

Tue Oct 28, 2025

Morning: 10:05am-12:45pm

  • Installed 2nd sliding door handle/lock and adjusted roller (~5min total)
  • Put up R38 fiberglass insulation into the ceiling, covered about 5 rows

Lunch: 12:45pm-1:45pm

Afternoon: 1:45pm-5:15pm

  • Sealed cracks & gaps between wall modules & rafters/taper with spray foam
  • Finished ceiling insulation in the first 2 house modules
Ceiling insulation
  • Started insulating wall modules in house module 1 with R19 fiberglass
Wall insulation
  • Started taking off some of the floor level OSB strips to fill in gaps behind them with spray foam (in house module 3)

Mon Oct 27, 2025

Morning: 10:05am-2:30pm

  • Helped attach roof rafter braces
  • Started attaching some PV panels

Lunch: 2:30pm-3:30pm

Afternoon: 3:30pm-6:20pm

  • Measured out PV spacing on most runners
  • Attached front PV mounts on most runners
  • Finished installing first row of PV panels


Evening (non-work):

  • Spent 2h after work learning/trying out FreeCAD 1.0