Cost of CEB Block

From Open Source Ecology
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

Commercial

  • $1 for unstabilized, $1.20 for stabilized - [1]

Proejcted OSE Costs - Expected to be Attained at Summer X 2021

Error creating thumbnail: File missing
Hint: Absolute production cost ranges from 5 to 40 cents per block under the assumptions below. Note - soil digging is not included, which adds 1.5 gallon per hour cost of fuel to the overall operation.
  • Costs based on availability of on-site soil
  • 6 block per minute machine - 8 hour shift - 1 gallon per hour for CEB, 0.5 gallon per hour for tractor (25% duty cycle assuming nearby pile of soil that has already been dug), one gallon per hour for soil mixer, local clay soil, 10% cement stabilized
  • Total costs for 2880 block:
  1. 2.5 gal* 8=20 gal fuel = $50 at current gas prices
  2. Cement - $10 per bag for 100 block - 29 bags of cement - $290
  3. Labor - $25/hr for tractor operator, $15/hr for stacking block on pallets x2 - $440/day
  4. Water - 20 ml/block = 58 liters = 15 gallons at 2 cents - 30 cents in water
  5. Plastic wrap
  6. Pallets

Total costs -

edit spreadsheet

Upload of Key Costs

Error creating thumbnail: File missing