#ED to NOLA July 26-29, 2013 | |||
#(T) End of September - Construction Site Manager on site - (T) Chris Reinhart - reinhart.christopher@gmail.com | |||
#Designate FeF media days | |||
#Isaac Wilder - Internet Options - Identify a time to sitdown with Isaac Wilder and discuss a possible relationship/partnership with [http://thefnf.org/people-2/ Free Network Foundation] (Follow up with Isaac when discussion date is identified) | |||
#Steve Long & John Biggs to FeF for filming an OSE "Makers" episode - [http://techcrunch.com/video/techcrunch-makers/ TechCrunch Makers] - Determine the best upcoming machine build or Microhouse build for filming (Follow up with Steve when dates are identified) | |||
#Close out interview with Cory and Leandra | |||
##OSE Operations - How OSE Executive Staff works, company processes < ongoing development of company processes | |||
##OSE Lessons Learned - personal, OSE, product design, and manufacturing, etc. - purpose > to create recruiting video and improve DPV experience | |||
##Internship Evaluations - see email doc | |||
#ED to approve [https://docs.google.com/a/opensourceecology.org/document/d/1ajV3STgn-4k4_Kn0zwo2eEbmyy7C-UxM9N1e7lK8b1Q/edit Employee Handbook] | |||
#Workshop | |||
##Inventory Storeroom or Designated Area | |||
##Tools Storeroom or Designated Area | |||
##Finished Goods Designated Area | |||
##One initial overhaul asap | |||
##routine organization and inventory prior to each build | |||
##Develop Workshop Safety and Orientation Course - [http://opensourceecology.org/wiki/Workshop_Guidelines Workshop Guidelines] | |||
##[https://www.osha.gov/pls/oshaweb/owasrch.search_form?p_doc_type=STANDARDS&p_toc_level=1&p_keyvalue=1910 OSHA - General Industry] | |||
###[https://www.osha.gov/pls/oshaweb/owadisp.show_document?p_table=STANDARDS&p_id=9735 OSHA - Occupational Noise Exposure] | |||
###[https://www.osha.gov/pls/oshaweb/owadisp.show_document?p_table=STANDARDS&p_id=10118 OSHA - Personal Protective Equipment] | |||
###[https://www.osha.gov/pls/oshaweb/owadisp.show_document?p_table=STANDARDS&p_id=10121 OSHA - General Environmental Controls] | |||
#Dozuki orientation | |||
##for Executive Staff | |||
##for collaborators | |||
#6 in 60 Open Hotwash - all information to be inputed into [http://opensourceecology.org/wiki/Prototype_Assessment Prototype Assessments] | |||
#LifeTrac 5 Open Hotwash - all information to be inputed into [http://opensourceecology.org/wiki/Prototype_Assessment Prototype Assessments] | |||
#Infrastructure assessment - purpose to identify needed improvements and prioritize | |||
##Designated Trash Area | |||
#Schedule ED to conduct Google Hangout with the True Fans every 2 weeks | |||
#Monthly Truefans newsletter | |||
#Creation of a Media and Communications Strategy - press package, social media strategy | |||
#Schedule weekly Design Sprints - physical space | |||
#Schedule media interview with Scott Mann, The Permaculture Podcast - 930am and 4pm EST, asked for about an hour of time | |||
#Sans Retreat - integrate fun events into OSE's ongoing schedule - to include DPVs - this aims to solve overworking Executive Staff & DPVs | |||
##[http://kansascity.royals.mlb.com/schedule/sortable.jsp?c_id=kc Royals] - 1hr 7min south of Maysville | |||
##[http://www.stjomo.com/see-do/entertainment-nightlife/ St. Jo nightlife] | |||
##[http://www.stjomo.com/see-do/arts-culture/ St. Jo art & culture] | |||
#Time for Ops Man to review and implement [https://www.osha.gov/index.html OSHA] standards | |||
#Refine/review Community Standards | |||
##OSHA standards | |||
##Address why DPVs are not reading the standards prior to arriving |
Revision as of 18:18, 21 July 2013
Deliverables are in bold
Mon July 22, 2013
- Identify which Development Process will be templated into Project Manager - currently there are 3 draft processes
- Design Process - Draft created by ED and TechComManager
- Design/Build Process - Draft created by Product Lead with ED collaboration
- Design/Build Development Checklist - Product Lead Design/Build Process with ED checklist incorporated
- Build a Development Process Ribbon to represent timelines - time permitting prior to July 22, input example here
- Template Development Process into Project Manager or adjust the template Audrey has already worked
- Identify which projects are currently ongoing
- 6 in 60 closeout
- Hydrafabber
- CNC Torch Table
- Welder
- OSCar
- Articulated Tractor
- Microhouse
- Identify where in the above Development Process Ribbon each project is located
- In excel, build schedule incorporating ongoing projects and Product Lead Schedule and Development Process Ribbons - this will allow us to tentatively plan, easily moving around projects
- Upload schedule into Project Manager - in the future Project Manager will be the first tool to scheduling, but right now this step is necessary > scheduling is the primary focus and by using familiar tools, scheduling will remain the primary focus
- Depending which development process is chosen, create a standard module landing page on the wiki - time permitting prior to July 22, input example here
- Discuss/determine how tasking will be inputted into Project Manager - Under program umbrellas? What are OSE programs? Are they areas of responsibility each staff member oversees?
Tue July 23, 2013
Wed July 24, 2013
- Process Development: Identify protocols that are needed now, establishing ownership and deadlines for completion.
- Input tasking out of this discussion into Project Manager
Additional Scheduling Items
- ED to NOLA July 26-29, 2013
- (T) End of September - Construction Site Manager on site - (T) Chris Reinhart - reinhart.christopher@gmail.com
- Designate FeF media days
- Isaac Wilder - Internet Options - Identify a time to sitdown with Isaac Wilder and discuss a possible relationship/partnership with Free Network Foundation (Follow up with Isaac when discussion date is identified)
- Steve Long & John Biggs to FeF for filming an OSE "Makers" episode - TechCrunch Makers - Determine the best upcoming machine build or Microhouse build for filming (Follow up with Steve when dates are identified)
- Close out interview with Cory and Leandra
- OSE Operations - How OSE Executive Staff works, company processes < ongoing development of company processes
- OSE Lessons Learned - personal, OSE, product design, and manufacturing, etc. - purpose > to create recruiting video and improve DPV experience
- Internship Evaluations - see email doc
- ED to approve Employee Handbook
- Workshop
- Inventory Storeroom or Designated Area
- Tools Storeroom or Designated Area
- Finished Goods Designated Area
- One initial overhaul asap
- routine organization and inventory prior to each build
- Develop Workshop Safety and Orientation Course - Workshop Guidelines
- OSHA - General Industry
- Dozuki orientation
- for Executive Staff
- for collaborators
- 6 in 60 Open Hotwash - all information to be inputed into Prototype Assessments
- LifeTrac 5 Open Hotwash - all information to be inputed into Prototype Assessments
- Infrastructure assessment - purpose to identify needed improvements and prioritize
- Designated Trash Area
- Schedule ED to conduct Google Hangout with the True Fans every 2 weeks
- Monthly Truefans newsletter
- Creation of a Media and Communications Strategy - press package, social media strategy
- Schedule weekly Design Sprints - physical space
- Schedule media interview with Scott Mann, The Permaculture Podcast - 930am and 4pm EST, asked for about an hour of time
- Sans Retreat - integrate fun events into OSE's ongoing schedule - to include DPVs - this aims to solve overworking Executive Staff & DPVs
- Royals - 1hr 7min south of Maysville
- St. Jo nightlife
- St. Jo art & culture
- Time for Ops Man to review and implement OSHA standards
- Refine/review Community Standards
- OSHA standards
- Address why DPVs are not reading the standards prior to arriving