=Day 4 - SEH 2 Wall Design - Day 1 of Build=
<html> <iframe src="https://docs.google.com/presentation/d/e/2PACX-1vT6o1OY9fs1F7VG_3WJTklDF6GWDa38Z7UJSysrFC0B32dBdicGh5cUznpDBRjihEP-QdLwO4jyMOs4/embed?start=false&loop=false&delayms=3000" frameborder="0" width="480" height="389" allowfullscreen="true" mozallowfullscreen="true" webkitallowfullscreen="true"></iframe> </html>
[https://docs.google.com/presentation/d/1VR3zrHXGABWap2esgIhsAX1nN_TGQsDZoAbmVcg0Xdg/edit#slide=id.gb328b2d63d_0_9 edit]
=Seed Home Build Status=
[https://docs.google.com/spreadsheets/d/1qj4jscvrLyvwBTlUVRyJSC-ETpoR4CJ266BdG0Ly4AM/edit?usp=sharing| Wall Module Build Status]
=Schedule for the Next 10 Days=
*[[120 Design Lessons - Day 5]] - Day 1 - Walls. 38. 38 walls take 14 feet to store.
*[[120 Design Lessons - Day 6]] - Day 2 - Walls Finish.
*[[120 Design Lessons - Day 7]] - Day 3 - Doors and Windows
*[[120 Design Lessons - Day 8]] - Day 4 - Interior Walls
*[[120 Design Lessons - Day 9]] - Day 5 - Prepare joist hangers and blocking
*[[120 Design Lessons - Day 10]] - Day 6 - Garage Materials
*[[120 Design Lessons - Day 11]] - Day 7 - Install - first Floor walls, second story platform, second story walls
*[[120 Design Lessons - Day 12]] - Day 8 - Install Garage
*[[120 Design Lessons - Day 13]] - Day 9 - Install Roof
*[[120 Design Lessons - Day 14]] - Day 10 - Interior - paneling, ceiling, bathroom, kitchen, electrical runs
=Notes=
=Template=
<html>
<html>



Latest revision as of 22:20, 15 July 2021

Day 4 - SEH 2 Wall Design - Day 1 of Build

edit

Seed Home Build Status

Wall Module Build Status

Schedule for the Next 10 Days

Notes

Template