=Sun, Mar 9, 2014=
=Wed, Mar 12, 2014=
At Infrastructure meeting, discussed needs of MicroHouse 1 and improvements for MicroHouse 2
Morning meeting
*Ensure that we are documenting our activities
**15 min documentation sprint


MicroHouse 1
=Tues, Mar 11, 2014=
*Documentation needs consolidation
**Collect data from [http://opensourceecology.org/wiki/MicroHouse_Collaboration_2014/ MicroHouse Collaboration 2014] and input to [https://docs.google.com/spreadsheet/ccc?key=0ArpE5Y9PpJCXdDhPbmh6aXYxQ2NDWG5jWDZqUFozR2c#gid=1/ MicroHouse1 Development Board]
 
MicroHouse 2
*Flooring
**CEBs should be cured, 30-60 days prior to use
**CEBs crack and flake from stresses over time
*Modular roof
**Must be able to be installed on upper frame concurrently while CEB wall is being laid below
***Safety primary concern
**Looking for new concepts on the roof construction method


Work
Work
*Painted interior door trims
*Started to replace high window where stove pipe was.
**Stopped, on hold for clear caulk
*Plumbing in MicroHouse 1
*Whitewash HabLab swarm, various tasks


=Mon, Mar 10, 2014=
=Mon, Mar 10, 2014=
Morning meeting (in priority order)
Infrastructure meeting ToDo list (in priority order)
*1) Evaluate direct driveway to HabLab vs. path from entry near Workshops (1 and 2)
*1) Evaluate direct driveway to HabLab vs. path from entry near Workshops (1 and 2)
*2) New workshop will go between Workshop 1 (oldest) and Workshop 2 (newest)
*2) New workshop will go between Workshop 1 (oldest) and Workshop 2 (newest)
Line 27: Line 21:
*6) Re-roofing Greenhouse (attached to Workshop 2)
*6) Re-roofing Greenhouse (attached to Workshop 2)


MicroHouse ToDo:
MicroHouse 1 ToDo:
*Site cleanup
*Site cleanup
*Documentation
*Documentation
Line 34: Line 28:
*Built platform for front entry to HabLab
*Built platform for front entry to HabLab


=Sun, Mar 9, 2014=
At Infrastructure meeting, discussed needs of MicroHouse 1 and improvements for MicroHouse 2


=Mon, Mar 11, 2014=
MicroHouse 1
*Documentation needs consolidation
**Collect data from [http://opensourceecology.org/wiki/MicroHouse_Collaboration_2014/ MicroHouse Collaboration 2014] and input to [https://docs.google.com/spreadsheet/ccc?key=0ArpE5Y9PpJCXdDhPbmh6aXYxQ2NDWG5jWDZqUFozR2c#gid=1/ MicroHouse1 Development Board]
 
MicroHouse 2
*Flooring
**CEBs should be cured, 30-60 days prior to use
**CEBs crack and flake from stresses over time
*Modular roof
**Must be able to be installed on upper frame concurrently while CEB wall is being laid below
***Safety primary concern
**Looking for new concepts on the roof construction method


Work
Work
*Started to replace high window where stove pipe was.
*Painted interior door trims
**Stopped, on hold for clear caulk
*Plumbing in MicroHouse 1
*Whitewash HabLab swarm, various tasks

Revision as of 14:49, 12 March 2014

Wed, Mar 12, 2014

Morning meeting

  • Ensure that we are documenting our activities
    • 15 min documentation sprint

Tues, Mar 11, 2014

Work

  • Started to replace high window where stove pipe was.
    • Stopped, on hold for clear caulk
  • Plumbing in MicroHouse 1
  • Whitewash HabLab swarm, various tasks

Mon, Mar 10, 2014

Infrastructure meeting ToDo list (in priority order)

  • 1) Evaluate direct driveway to HabLab vs. path from entry near Workshops (1 and 2)
  • 2) New workshop will go between Workshop 1 (oldest) and Workshop 2 (newest)
  • 3) Pool - Delivery expected early this week
  • 4) MicroHouse
  • 5) Camp ground (for Summer visitors)
  • 6) Re-roofing Greenhouse (attached to Workshop 2)

MicroHouse 1 ToDo:

  • Site cleanup
  • Documentation

Work

  • Built platform for front entry to HabLab

Sun, Mar 9, 2014

At Infrastructure meeting, discussed needs of MicroHouse 1 and improvements for MicroHouse 2

MicroHouse 1

MicroHouse 2

  • Flooring
    • CEBs should be cured, 30-60 days prior to use
    • CEBs crack and flake from stresses over time
  • Modular roof
    • Must be able to be installed on upper frame concurrently while CEB wall is being laid below
      • Safety primary concern
    • Looking for new concepts on the roof construction method

Work

  • Painted interior door trims