Introduction

Different support levels indicate different rates of development.

Zero Budget Program

Under zero-budget operation with on-demand fund-raising of about $2k/month, we can:

  • 9.27.09 - Finish mud sprayer, test on CEB structure walls
  • 9.28-10.3.09 - First week of October, CEB Prototype II testing - 5000 bricks pressed
  • 10.5.09 - 10.31.09 - CEB Prototype III Build; addition of automation to hydraulic system
    • Main issues - hydraulic solenoids, Arduino control limit switch logic integration
  • November 1 , 2009 - Product Release, CEB Press. Initial release includes:
    • Design drawings (help needed)
    • Fabrication documentation (at least from Prototype II fabrication)
    • Cost Structure - $2500 for DIY production (labor discounted); $7000 for turnkey product; price may be adjusted after production optimization
    • Factor e Farm production level - 4 machines per month initially, may be scaled if needed
  • November 2-30 - Tractor Prototype 2 with Power Cube 2
  • December - Tractor Prototype 3 with existing Power Cubes

Accelerated Program Under $10k budget operation with grid connection

There is a possibility of bringing some skilled people into the operation, but the constraint is to survive December-February weather. See Average_Temperature_in_Kansas_City.

Under the condition that local support can be gathered, then a combination of camper and heated Solar Cubicles would be acceptable. Heating can be accomplished with a longwood stove, which can be fitted with a heat exchanger.

Scenario 1:

  • Local help to dismantle and move Solar Cubicle to new site. 1 Day.

Acceleration Budget

  • Camper rental - ?
  • Electrical connection - ?
  • Water hookup - ?
  • Propane heat -
  • Food bank access -