CEB Press/Manufacturing Instructions/Soil loading drawer
Jump to navigation
Jump to search
Main > Housing and construction > CEB Press > CEB press building instructions
Tools Required
Materials Required
- 1/2”x7”x12” (4)
- 1/4”x4”x6” tubing
- 1/4”x6”x14” (2) – bend at 4.5” the short way
- 1/4”x2”x2” angle, 12” long
- 1/4”x8”x12.5” plate
- 1/4”x8x12” plate, bent at 2” the long way
- 1”x1”x1/8”, 6” long (2)
Diagrams
Fabrication Steps
(note: part numbers refer to the recently-published parts list)
- Line up the Inner and Outer Rails (S27, S28) and clamp them together with vise grips.
- Clamp the Sides (S29), Press Plate (S26), Tube (S24) and Back (S22) and the rails together with vise-grips and C-Clamps.
- Tack weld the clamped drawer at a few locations down to prevent warping when it is welded together.
- Complete the welding joints, welding at different locations as you go to prevent warping.
- Check the completed drawer to ensure that it is still straight.
- If they are not straight, the rails may need to be adjusted to ensure that the bearings will roll fit them correctly; if the drawer is not even and aligned, it may not fit properly in the frame.
- Weld the Cylinder Tongue (S23) to the centre of the Back (S22) of the Drawer.