Based on Backhoe Boom Range of Motion Analysis, the procedure is:

  1. Mount a 2x4 hole standard bonding plate with 4 holes showing at top of boom.
  2. Bolt plate using 2 holes only so mount point is 10" above tubing
  3. Weld assist for proper hold

Done. Now to stick. See File:BoomROM.dxf for Test-Driven Design that was used.