Introduction: Extreme Management
Project evaluation and review is critical to project management. Extreme Management is OSE's version of an open, collaborative method with a focus on documentation of work product. All results are readily accessible in one click from a graphical index/overview platform. Extreme Management builds upon the concept of PERT charts and Critical Path Diagrams, including clear Work Breakdown Structures.
The requirements for open project management platform are:
- Project is readily reviewable by a brief examination of management platform, including one-click access to all content
- Work product is one-click accessible from management platform
- Can be displayed on a cloud-embeddable-linkable platform such as Google Docs
- Project status and work product can be viewed from anywhere and updated readily
- Platform can be embedded into any other platform and that the updates in the display are updated readily
- Work product can be linked to a graphical index of the Extreme Management platform. This adds a focus of documenting work product
- Budget, timeline, sequence, duration are visible
Sample PERT Index
Sample Tracking Spreadsheet with Gantt Chart
Implementation
Execution of a complex task follows these steps:
- Start with a clear Work Breakdown Structure
- OSE PERT Chart shows milestones, expected start time and duration, and actual end time, dependencies, and order of execution. This constitutes a scope and sequence of a project. Each milestone links to a spreadsheet.
- Spreadsheet shows tasks from the Work Breakdown Structure, their predicted and actual times, links to work product, and planned + actual cost are shown on a spreadsheet.
How it Works
- A project page displays the PERT chart and spreadsheed, and allows anyone to observe and assess overall progress in minutes. Spreasheet shows work breakdown by day.
- The single PERT chart is sufficient to access all information about a project.
- The PERT chart links to a master spreadsheet of tasks.
- The PERT Chart is updated with actual times and budgets to allow for learning
- The spreasheet shows a Gantt chart, which is created by shading in the days
- The spreadsheet row show planned and actual values for each. Shade in actual values in Gantt section with dark green.