Top Roof Section Module Build Instructions: Difference between revisions

From Open Source Ecology
Jump to navigation Jump to search
No edit summary
 
(4 intermediate revisions by the same user not shown)
Line 2: Line 2:
#Cut 16' long members to 16' exactly.  
#Cut 16' long members to 16' exactly.  
#Mark location of purlins 4' on center
#Mark location of purlins 4' on center
#Cut 4 purlins and 2 end caps for roof frame - fitted between long 16' members so that the panel is 3' wide. Note that we are not using plywood here.
#Cut 4 purlins and 2 end caps for roof frame - fitted between long 16' members so that the panel is 3' wide. Note that we are not using plywood here.
#Screw 2 long members and 2 end caps together using [3] 3" screws
#Screw 2 long members and 2 end caps together using [3] 3" screws
#Screw in purlins at marked locations
#Screw in purlins at marked locations
#Invert  
#Invert on sawhorses and staple tyvek base layer upon which insulation will sit
#Re-invert to right-side-up and insert insulation
#Cover the top of panel with Tyvek as a moisture barrier under metal roofing. Note: do not install metal roofing - it is not possible to line up the seams this way, so roof metal goes on last.
 
=Tools and Materials=
*3/8" Stapler
*Miter saw
*Pencil
*Metal roofing screws (for install)
*Tyvek
*2x6s
*Roof metal - (after roof is in place)
*Flashing - (after roof is in place)
*Roof metal ridge seal foam
*Insulation
*Pro-Rib vented seal - ? - [http://www.menards.com/main/building-materials/pole-barn-post-frame-materials/tools-accessories/pro-rib-vented-closure-4-panels/p-1808123-c-5713.htm]
*Pro-Rib outside closure - [http://www.menards.com/main/building-materials/pole-barn-post-frame-materials/tools-accessories/pro-rib-outside-closure-4-pack/p-1808125-c-5713.htm]
*Pro-Rib inside closure - [http://www.menards.com/main/building-materials/pole-barn-post-frame-materials/tools-accessories/pro-rib-reg-inside-closure-4-pack/p-1808126-c-5713.htm]


=Visual Animation in Sketchup=
=Visual Animation in Sketchup=

Latest revision as of 04:34, 21 September 2014

Script

  1. Cut 16' long members to 16' exactly.
  2. Mark location of purlins 4' on center
  1. Cut 4 purlins and 2 end caps for roof frame - fitted between long 16' members so that the panel is 3' wide. Note that we are not using plywood here.
  2. Screw 2 long members and 2 end caps together using [3] 3" screws
  3. Screw in purlins at marked locations
  4. Invert on sawhorses and staple tyvek base layer upon which insulation will sit
  5. Re-invert to right-side-up and insert insulation
  6. Cover the top of panel with Tyvek as a moisture barrier under metal roofing. Note: do not install metal roofing - it is not possible to line up the seams this way, so roof metal goes on last.

Tools and Materials

  • 3/8" Stapler
  • Miter saw
  • Pencil
  • Metal roofing screws (for install)
  • Tyvek
  • 2x6s
  • Roof metal - (after roof is in place)
  • Flashing - (after roof is in place)
  • Roof metal ridge seal foam
  • Insulation
  • Pro-Rib vented seal - ? - [1]
  • Pro-Rib outside closure - [2]
  • Pro-Rib inside closure - [3]

Visual Animation in Sketchup

See scenes in this Sketchup animation.

Download file - File:Toproofbuild.skp (uses wiki version control)


Warehouse version -may not be updated - Warehouse has no versioning: