The OBI + OSE Off-Grid PV Workshop is a workshop where you will learn to design and install a complete, rooftop, 3kW, off-grid PV system for a home - for $3000 in materials. The workshop involves a complete install of a 3kW system from the roof mounting system - to a control panel with power measurement, a battery bank, wall outlets, and a super-efficient refrigerator. We will show you how to convert a chest freezer to a super-efficient refrigerator which draws only 8 watts of power on average. This 12x less than an average refrigerator - and is one of the critical elements that allow for building a low cost system with a small battery bank - as the main load at night is a refrigerator. We will measure all the loads in the system - so that a power management strategy emerges for running all loads in summer and winter. The intended audience is anyone who wants to learn about PV systems first hand - and especially anyone who wants to pay their last utility bill at a cost of $3k for a complete off-grid system like the one in the workshop.
=Program=
=Program=
Feb 4 = T-120
*June 4-6, 2018
*Assets - Design Book given to participants. Others can purchase the book online, printed or e-book on the OBI site, OSE site
*Preparation required:
:*All materials on-site at T-30
:*All materials ordered at T-60
==Day 1==
==Day 1==
*8 AM - Intro + discussion
*8 AM - Intro. Design Overview
*9-12 - Railings Build
*9-12 - Build of Railings + Roof Mounts Build
*12-1 - Lunch
*1-2 - Afternoon Design Discussion
*2-5 - Installation of PV Panels + Wiring
*Dinner 6-7
*Discussion, Q&A 7-8
 
==Day 2==
*8 AM - Control Panel Design Discussion
*9-12 - Build of Control Panel
*12-1 - Lunch
*12-1 - Lunch
*1-2 - PV Panel Wiring
*1-2 - Afternoon Design Discussion: Safety, code compliance
*2-5 - Install of Wiring, breakers, and outlets
*Dinner 6-7
*Discussion, Q&A 7-8


==Day 3==
*8 AM - Morning Design Discussion - How to Test the System
*9-12 - Installing measurement devices, measuring power usage, and Power On.
*12-1 - Disconnection from the Grid Ceremony + Lunch
*1-2 - Energy Management Discussion: Load Strategy + Super-efficient Refrigerator
*2-5 - Building a Super-efficient refrigerator controller + Install of SuperFridge
*Dinner 6-7
*Discussion, Q&A 7-8


*PV Panels
=Links=
=Links=
*[[Aquaponics Workshop]]
*[[Aquaponics Workshop]]

Revision as of 04:48, 4 February 2018

https://docs.google.com/document/d/18nyOgvA7CS7n3tYejE1_B3cf6sx6MsTHimqvOp1hrFM/edit

Overview

The OBI + OSE Off-Grid PV Workshop is a workshop where you will learn to design and install a complete, rooftop, 3kW, off-grid PV system for a home - for $3000 in materials. The workshop involves a complete install of a 3kW system from the roof mounting system - to a control panel with power measurement, a battery bank, wall outlets, and a super-efficient refrigerator. We will show you how to convert a chest freezer to a super-efficient refrigerator which draws only 8 watts of power on average. This 12x less than an average refrigerator - and is one of the critical elements that allow for building a low cost system with a small battery bank - as the main load at night is a refrigerator. We will measure all the loads in the system - so that a power management strategy emerges for running all loads in summer and winter. The intended audience is anyone who wants to learn about PV systems first hand - and especially anyone who wants to pay their last utility bill at a cost of $3k for a complete off-grid system like the one in the workshop.

Program

Feb 4 = T-120

  • June 4-6, 2018
  • Assets - Design Book given to participants. Others can purchase the book online, printed or e-book on the OBI site, OSE site
  • Preparation required:
  • All materials on-site at T-30
  • All materials ordered at T-60

Day 1

  • 8 AM - Intro. Design Overview
  • 9-12 - Build of Railings + Roof Mounts Build
  • 12-1 - Lunch
  • 1-2 - Afternoon Design Discussion
  • 2-5 - Installation of PV Panels + Wiring
  • Dinner 6-7
  • Discussion, Q&A 7-8

Day 2

  • 8 AM - Control Panel Design Discussion
  • 9-12 - Build of Control Panel
  • 12-1 - Lunch
  • 1-2 - Afternoon Design Discussion: Safety, code compliance
  • 2-5 - Install of Wiring, breakers, and outlets
  • Dinner 6-7
  • Discussion, Q&A 7-8

Day 3

  • 8 AM - Morning Design Discussion - How to Test the System
  • 9-12 - Installing measurement devices, measuring power usage, and Power On.
  • 12-1 - Disconnection from the Grid Ceremony + Lunch
  • 1-2 - Energy Management Discussion: Load Strategy + Super-efficient Refrigerator
  • 2-5 - Building a Super-efficient refrigerator controller + Install of SuperFridge
  • Dinner 6-7
  • Discussion, Q&A 7-8