CEB Calculations: Difference between revisions

From Open Source Ecology
Jump to navigation Jump to search
(Created page with "*1 cubic yard of brick is - 27x6 block x 20lb = around 3000 lb - about 150 block (162 specifically) *OSE required throughput for brick production is at minimum 6 block per min...")
 
(No difference)

Latest revision as of 16:51, 8 April 2018

  • 1 cubic yard of brick is - 27x6 block x 20lb = around 3000 lb - about 150 block (162 specifically)
  • OSE required throughput for brick production is at minimum 6 block per minute - 360 per hour - 2 cubic yards per hour.
  • If soil mixer is 275 hp for 100 cubic yards per hour for soil cement slurry - we would in principle need only 5 hp for mixing