Build Certification: Difference between revisions
Jump to navigation
Jump to search
(Created page with "=Procedure= #Build frame. 3 detailed Finished Pictures showing the amount of epoxy used on inside bottom, inside sides, and inside top. Time. #Build Y Left Axis twice. Finishe...") |
|||
Line 4: | Line 4: | ||
#Build Y Right Axis twice. Finished Picture from the opposite side of the motor. Time. | #Build Y Right Axis twice. Finished Picture from the opposite side of the motor. Time. | ||
#Build X axis. Finished picture from motor side. Time | #Build X axis. Finished picture from motor side. Time | ||
#Build extruder assembly. | |||
#Build heated bed (PEI addition + twist white wire around red. Finished icture from both sides. Time. | #Build heated bed (PEI addition + twist white wire around red. Finished icture from both sides. Time. | ||
#Build control panel. Finished picture from both sides. Time. | #Build control panel. Finished picture from both sides. Time. | ||
Line 9: | Line 10: | ||
#Mount the X axis. Finished picture. Time. | #Mount the X axis. Finished picture. Time. | ||
#Mount heated bed. Finished picture. Time. | #Mount heated bed. Finished picture. Time. | ||
#Mount | #Mount extruder. Finished picture. Time. | ||
#Do cable chain and all wire routing and tidying. | #Do cable chain and all wire routing and tidying. | ||
# | # |
Revision as of 16:57, 12 November 2018
Procedure
- Build frame. 3 detailed Finished Pictures showing the amount of epoxy used on inside bottom, inside sides, and inside top. Time.
- Build Y Left Axis twice. Finished Picture from the side opposite of the motor. Time.
- Build Y Right Axis twice. Finished Picture from the opposite side of the motor. Time.
- Build X axis. Finished picture from motor side. Time
- Build extruder assembly.
- Build heated bed (PEI addition + twist white wire around red. Finished icture from both sides. Time.
- Build control panel. Finished picture from both sides. Time.
- Mount Y axes and Z axes. Finished Picture. Time.
- Mount the X axis. Finished picture. Time.
- Mount heated bed. Finished picture. Time.
- Mount extruder. Finished picture. Time.
- Do cable chain and all wire routing and tidying.