An individual should be set up for on-demand production of a minimum of 30 drills per month.
The proposed format is using 3 dedicated production days - the rest being 3D printing in the background, and possibly other automated jobs that run without attendance once set up.
Each production day should yield 12 drills assembled in a period of 8 hours - assuming all parts are printed and avialable for assembly. The 8 hours does not consider printing and part manufacturing, outside of potential minor fabrication tasks. Ie - all materials must be on hand.
Set up time for engaging a production run should be 1 hour. That means a dedicated space is available, without requiring setup time.