Under Construction Phase Inspections: Difference between revisions

From Open Source Ecology
Jump to navigation Jump to search
Line 14: Line 14:
*Includes all enclosures - breaker boxes, outlet boxes
*Includes all enclosures - breaker boxes, outlet boxes
*''Switches, receptacles and fixtures should not be installed at the rough-in.''
*''Switches, receptacles and fixtures should not be installed at the rough-in.''
=Plumbing and Mechanical=
*Prior to any enclosure, plumbing is inspected
*Includes water, drain, waste, and vents
*Includes HVAC vents; range, dryer and bathroom vents; water heater and venting; others. If water heater is not fuel-fired,
=Framing=
=Framing=
*Includes both interior and exterior walls, load bearing or not. Inspection is done after all rough-in plumbing and electrical, and ducting is in place.
*Includes both interior and exterior walls, load bearing or not. Inspection is done after all rough-in plumbing and electrical, and ducting is in place.

Revision as of 04:40, 10 January 2022

Document for Alaska - [1]

Site Plan

  • this is the first inspection

Foundation

Rough-in inspections include plumbing, electrical, and framing:

Electrical

  • includes wiring and breakers
  • Includes ground conductor
  • Includes all enclosures - breaker boxes, outlet boxes
  • Switches, receptacles and fixtures should not be installed at the rough-in.

Plumbing and Mechanical

  • Prior to any enclosure, plumbing is inspected
  • Includes water, drain, waste, and vents
  • Includes HVAC vents; range, dryer and bathroom vents; water heater and venting; others. If water heater is not fuel-fired,

Framing

  • Includes both interior and exterior walls, load bearing or not. Inspection is done after all rough-in plumbing and electrical, and ducting is in place.