Under Construction Phase Inspections: Difference between revisions
Jump to navigation
Jump to search
No edit summary |
|||
Line 19: | Line 19: | ||
*Includes house wrap | *Includes house wrap | ||
=Electrical= | ==Electrical== | ||
*includes wiring and breakers | *includes wiring and breakers | ||
*Includes ground conductor | *Includes ground conductor | ||
Line 25: | Line 25: | ||
*''Switches, receptacles and fixtures should not be installed at the rough-in.'' | *''Switches, receptacles and fixtures should not be installed at the rough-in.'' | ||
=Plumbing and Mechanical= | ==Plumbing and Mechanical== | ||
*Prior to any enclosure, plumbing is inspected | *Prior to any enclosure, plumbing is inspected | ||
*Includes water, drain, waste, and vents | *Includes water, drain, waste, and vents | ||
*Includes HVAC vents; range, dryer and bathroom vents; water heater and venting; others. If water heater is not fuel-fired, | *Includes HVAC vents; range, dryer and bathroom vents; water heater and venting; others. If water heater is not fuel-fired, | ||
=Framing= | ==Framing== | ||
*Includes both interior and exterior walls, load bearing or not. Inspection is done after all rough-in plumbing and electrical, and ducting is in place. | *Includes both interior and exterior walls, load bearing or not. Inspection is done after all rough-in plumbing and electrical, and ducting is in place. |
Revision as of 04:49, 10 January 2022
References
Site Plan
- this is the first inspection
Grading Inspection
- This is inspected in Georgia.
Foundation
- Slab inspection happens before pouring
- Plumbing under-slab may be inspected prior to covering
Complete Rough
- Rough-in inspections include plumbing, electrical, and framing:
- Includes house wrap
Electrical
- includes wiring and breakers
- Includes ground conductor
- Includes all enclosures - breaker boxes, outlet boxes
- Switches, receptacles and fixtures should not be installed at the rough-in.
Plumbing and Mechanical
- Prior to any enclosure, plumbing is inspected
- Includes water, drain, waste, and vents
- Includes HVAC vents; range, dryer and bathroom vents; water heater and venting; others. If water heater is not fuel-fired,
Framing
- Includes both interior and exterior walls, load bearing or not. Inspection is done after all rough-in plumbing and electrical, and ducting is in place.