Time to Build a House: Difference between revisions
		
		
		
		
		
		Jump to navigation
		Jump to search
		
				
		
		
	
 (→Hours)  | 
				 (→Hours)  | 
				||
| Line 10: | Line 10: | ||
*4 months 6 men efficient build, 3br. Say it's 2000 sf - 4 mos * 960 (40*6 men *4 weeks) = 4000 hours. 2 man years per house. [https://www.quora.com/How-long-will-it-take-to-build-a-house?top_ans=82636192]  | *4 months 6 men efficient build, 3br. Say it's 2000 sf - 4 mos * 960 (40*6 men *4 weeks) = 4000 hours. 2 man years per house. [https://www.quora.com/How-long-will-it-take-to-build-a-house?top_ans=82636192]  | ||
*Framing - 225 hours per 1000 sf [https://www.quora.com/How-long-will-it-take-to-build-a-house?top_ans=82636192]  | *Framing - 225 hours per 1000 sf [https://www.quora.com/How-long-will-it-take-to-build-a-house?top_ans=82636192]  | ||
*1100 sf mostly alone - 4 mos = 800 hours [https://www.quora.com/How-long-will-it-take-to-build-a-house?top_ans=82636192]  | |||
Revision as of 09:51, 12 January 2022
- 12 month owner builder, 8 month custom, 6 months spec [1]
 - 6 Month Spec - [2].
 - Habitat NOVA - 12-16 months during COVID (conference communications)
 
Hours
- 1536 hours for a 600 sf house [3]. This would be 2600 hours for 1000 sf.
 - 1000 hours for 2000 sf - https://www.quora.com/How-many-man-days-does-it-take-to-build-a-typical-residential-house] assuming 6 day weeks of 8 hrs and one month of time with 5 person crew. Really?
 - 2 people 3 months 1500 sf [4] = 1200 hours
 - 3 guys 1 week 1200 sf [5]
 - 4 months 6 men efficient build, 3br. Say it's 2000 sf - 4 mos * 960 (40*6 men *4 weeks) = 4000 hours. 2 man years per house. [6]
 - Framing - 225 hours per 1000 sf [7]
 - 1100 sf mostly alone - 4 mos = 800 hours [8]