Tue May 31, 2022

Let's talk about it ! Just met with a guy who had experience in the KCMO permit process who had some good insights on streamlining

  • 5 days is possible but after the foundation is in (because who knows what you find when you start digging and need to address)
  • if you get a master plan approved into the title block, you don't need designs approved again on future builds
  • you can hire an approved 3rd party inspector architecture/structural engineer to fast track the inspection process.