Max Log: Difference between revisions
		
		
		
		
		
		Jump to navigation
		Jump to search
		
				
		
		
	
| (4 intermediate revisions by the same user not shown) | |||
| Line 6: | Line 6: | ||
| {{Timelog|Max2}} | {{Timelog|Max2}} | ||
| =Thu Oct 30, 2025= | |||
| Morning: 10:00am-12:00pm | |||
| * Trimmed PV runners | |||
| [[File:Flush runners.jpg|thumb|PV runners flush with cap]] | |||
| * Fixed up PV runner cap 2x4 on the 3rd module | |||
| * Folded up roof membrane at the south side to fit with PV runner cap 2x4s | |||
| [[File:End cap wrap.jpg|thumb|Wrapped & taped up end caps between modules]] | |||
| * Installed some 1x6 roof trim | |||
| [[File:Trim boards.jpg|thumb|1x6 trim board on roof]] | |||
| Lunch: - | |||
| Afternoon: 12:00pm-6:45pm | |||
| * Installed siding | |||
| [[File:Siding 3.jpg|thumb|Metal siding]] | |||
| * Cut opening for east side windows | |||
| [[File:Window holes.jpg|thumb|Cut window holes]] | |||
| * Installed flashing tar tape in both window frames | |||
| [[File:Window flashing tape.jpg|thumb|Window flashing tape]] | |||
| * Installed first window | |||
| [[File:Window installed.jpg|thumb]] | |||
| * Started installation of second window | |||
| =Wed Oct 29, 2025= | |||
| Morning: 10:10am-12:15pm | |||
| * Installed PV panels | |||
| [[File:Solar1.jpg|thumb|Solar panels closeup]] | |||
| [[File:Solar2.jpg|thumb|First row of solar panels installed]] | |||
| Lunch: 12:15pm-1:40pm | |||
| Afternoon: 1:40pm-7pm | |||
| * Finished installing PV panels | |||
| [[File:Solar3.jpg|thumb|Solar panel installation nearly complete]] | |||
| [[File:Solar4.jpg|thumb|Solar panel installation complete]] | |||
| * Trimmed roof membrane on east side of building to fit trim boards | |||
| * Started installing trim boards on roof | |||
| =Tue Oct 28, 2025= | =Tue Oct 28, 2025= | ||
Latest revision as of 04:44, 31 October 2025
Build Pictures
- Upload - [1]
Time Log
Write down morning work done, lunch time, and afternoon work done.
Thu Oct 30, 2025
Morning: 10:00am-12:00pm
- Trimmed PV runners
- Fixed up PV runner cap 2x4 on the 3rd module
- Folded up roof membrane at the south side to fit with PV runner cap 2x4s
- Installed some 1x6 roof trim
Lunch: -
Afternoon: 12:00pm-6:45pm
- Installed siding
- Cut opening for east side windows
- Installed flashing tar tape in both window frames
- Installed first window
- Started installation of second window
Wed Oct 29, 2025
Morning: 10:10am-12:15pm
- Installed PV panels
Lunch: 12:15pm-1:40pm
Afternoon: 1:40pm-7pm
- Finished installing PV panels
- Trimmed roof membrane on east side of building to fit trim boards
- Started installing trim boards on roof
Tue Oct 28, 2025
Morning: 10:05am-12:45pm
- Installed 2nd sliding door handle/lock and adjusted roller (~5min total)
- Put up R38 fiberglass insulation into the ceiling, covered about 5 rows
Lunch: 12:45pm-1:45pm
Afternoon: 1:45pm-5:15pm
- Sealed cracks & gaps between wall modules & rafters/taper with spray foam
- Finished ceiling insulation in the first 2 house modules
- Started insulating wall modules in house module 1 with R19 fiberglass
- Started taking off some of the floor level OSB strips to fill in gaps behind them with spray foam (in house module 3)
Mon Oct 27, 2025
Morning: 10:05am-2:30pm
- Helped attach roof rafter braces
- Started attaching some PV panels
Lunch: 2:30pm-3:30pm
Afternoon: 3:30pm-6:20pm
- Measured out PV spacing on most runners
- Attached front PV mounts on most runners
- Finished installing first row of PV panels
Evening (non-work):
- Spent 2h after work learning/trying out FreeCAD 1.0