8/18 Erected posts and poured concrete for new mill shed beside workshop.
8/20: Moved felled logs to stack behind mill shed. Spread old CEB across ground for new shop. Began clearing land with new box blade.
8/21: Cleared out felled walnut tree, deposited branches near wood chipper in orchard. Put usable walnut wood in a pile behind mill shed