MicroHouse 4 Foundation: Difference between revisions
Jump to navigation
Jump to search
No edit summary |
No edit summary |
||
(3 intermediate revisions by the same user not shown) | |||
Line 4: | Line 4: | ||
*2"x10" forms | *2"x10" forms | ||
*Stands 1-2" above floor | *Stands 1-2" above floor | ||
*Includes concrete pad for | *Includes concrete pad for [[Hydronic Stove]] and for bathroom | ||
*Provision must be made that CEB walls do not risk water damage in the event of house flooding via water leaks | *Provision must be made that CEB walls do not risk water damage in the event of house flooding via water leaks | ||
*Foundation plan facilitates installation of CEB floor | *Foundation plan facilitates installation of CEB floor | ||
*Foundation plan facilitates installation of hydronic heating | *Foundation plan facilitates installation of hydronic heating | ||
*Foundation plan facilitates installation of water and power lines in perimeter of floor | *Foundation plan facilitates installation of water and power lines in perimeter of floor | ||
*Makes provisions for extension of foundation on corners - via stubbing out of rebar | |||
<html><iframe src="https://docs.google.com/presentation/d/1JPAPZ-aQlmIyJKuo-oaJpedSHI3yzSOeFic4TItn5d0/embed?start=false&loop=false&delayms=3000" frameborder="0" width="960" height="569" allowfullscreen="true" mozallowfullscreen="true" webkitallowfullscreen="true"></iframe></html> |
Latest revision as of 16:42, 7 September 2014
Requirement
- 1' wide stem wall
- Shallow insulated footer
- 2"x10" forms
- Stands 1-2" above floor
- Includes concrete pad for Hydronic Stove and for bathroom
- Provision must be made that CEB walls do not risk water damage in the event of house flooding via water leaks
- Foundation plan facilitates installation of CEB floor
- Foundation plan facilitates installation of hydronic heating
- Foundation plan facilitates installation of water and power lines in perimeter of floor
- Makes provisions for extension of foundation on corners - via stubbing out of rebar