Truss Build Data: Difference between revisions
Jump to navigation
Jump to search
(3 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
=Thu Aug 7, 2025= | |||
*Doing mid section. One truss nailed in upside down. One not set 2' away from supporting truss. | |||
=Wed Aug 6, 2025= | |||
*Alex 6hr, 10-4:30, 1/2 hr lunch - 6 hr. | |||
*Boyz - 5:30 hr from 10 to 6 with break | |||
*Suzanne - couple hours for 5 trusses with the Family School Apprenticeship | |||
=Tue Aug 5, 2025= | =Tue Aug 5, 2025= | ||
*MJ 3 headers 3 hours including one miscut has to be cut down second time. | *MJ 3 headers 3 hours including one miscut has to be cut down second time. | ||
*Alex 10:30 am start | *Alex 10:30 am start - 8.5 hrs. | ||
*Simmonses - 10-6 with lunch | *Simmonses - 10-6 with lunch - 7:30 hrs each | ||
*Matthew - 4 PM to | *Matthew - 4 PM to 8 - 4 hrs | ||
=Mon Aug 4, 2025= | =Mon Aug 4, 2025= | ||
*MJ 1.5 hr for truss | *MJ 1.5 hr for truss |
Latest revision as of 21:53, 7 August 2025
Thu Aug 7, 2025
- Doing mid section. One truss nailed in upside down. One not set 2' away from supporting truss.
Wed Aug 6, 2025
- Alex 6hr, 10-4:30, 1/2 hr lunch - 6 hr.
- Boyz - 5:30 hr from 10 to 6 with break
- Suzanne - couple hours for 5 trusses with the Family School Apprenticeship
Tue Aug 5, 2025
- MJ 3 headers 3 hours including one miscut has to be cut down second time.
- Alex 10:30 am start - 8.5 hrs.
- Simmonses - 10-6 with lunch - 7:30 hrs each
- Matthew - 4 PM to 8 - 4 hrs
Mon Aug 4, 2025
- MJ 1.5 hr for truss
- Alex - 8.5 hrs
- Matthew - 7 hours
Sat Aug 2, 2025
About 12 working people. Start 8 AM to 6:30 PM.
Fri Aug 1, 2025
- Pour - 8hr with Porter, Sam, and Parley. Alex 8 hr. Dean 5:30 hr. Charles 6 hr.
Thu
- Built 40 trusses, 16', and 16 trusses 24' - 56 total. Day total one per half hour + me as support - if count me . I was cutting strips and end pieces, mostly organizing tools and efficiency. With me counts as 35 minutes per truss, which is poor.
- Alex 7 hr.
- Boys 6.5 hr x3
Wed Jul 30, 2025
- Porter, Sam, and Parley - 6 hr each. Did 6 headers and then some.
Tue
- 7.5 hr x3.. Simmons boys 25 reinforces 24 ft trusses, about 5 hr, total of 7.5 hr with 17 more simple wall modules, me helping on wall.
- Matthew 8 reinf truss 4 hr