Truss Build Data: Difference between revisions
Jump to navigation
Jump to search
(12 intermediate revisions by the same user not shown) | |||
Line 3: | Line 3: | ||
=Fri Aug 22, 2025= | =Fri Aug 22, 2025= | ||
*Matthew 8 hrs | *Matthew 8 hrs. Total hours for week were 30. | ||
*Total wall modules count for Hangar - 108 | *Total wall modules count for Hangar - 108. If over 6 days 108 are done, and 6 from before - total done is 6 days is 102/6 = 17 average per day? | ||
*Barry - | |||
=Thu Aug 21, 2025= | =Thu Aug 21, 2025= | ||
Line 10: | Line 11: | ||
*Boys - 6 hrs each - 9 to 3 but lunch? | *Boys - 6 hrs each - 9 to 3 but lunch? | ||
*Matthew - 8:15 hrs | *Matthew - 8:15 hrs | ||
*Aunnalee - 8 hrs. Total hours 32. | |||
*Barry - | |||
=Wed Aug 20, 2025= | =Wed Aug 20, 2025= | ||
*Lost track of numbers from Tue and Wed - but if 90 by Thursday - did we do 57 over Tue & Wed? Way too high. | |||
*Matthew - 8 hrs | *Matthew - 8 hrs | ||
*Aunnalee - 8 hrs | |||
*Barry - | |||
=Tue Aug 19, 2025= | =Tue Aug 19, 2025= | ||
*Matthew 5:45 - | *Matthew 5:45 - | ||
*Alex - not here. | *Alex - not here. | ||
*Barry - | *Barry - arrived. 3 PM | ||
*Aunnalee - 8 hr | |||
=Mon Aug 18, 2025= | =Mon Aug 18, 2025= | ||
*Matthew, Aunnalee, Jacob - 8 hr x3 = 24/15 = 1.6. Same as Saturday? 3x instead of 1x. Jig issues - fixed. | *Matthew, Aunnalee, Jacob - 8 hr x3 = 24 hrs/15 modules done today= 1.6. Same as Saturday? 3x instead of 1x. Jig issues - fixed. | ||
*27 total modules in 2 days. But there were 6 from before, so total is '''33 done.''' | *27 total modules in 2 days. But there were 6 from before, so total is '''33 done.''' | ||
Latest revision as of 21:23, 23 August 2025
Sat Aug 23, 2025
- Boys 1-5 4 hr Start on T-modules
Fri Aug 22, 2025
- Matthew 8 hrs. Total hours for week were 30.
- Total wall modules count for Hangar - 108. If over 6 days 108 are done, and 6 from before - total done is 6 days is 102/6 = 17 average per day?
- Barry -
Thu Aug 21, 2025
- 18 made - 3 stacks acc to Matthew - thus count at 90 walls
- Boys - 6 hrs each - 9 to 3 but lunch?
- Matthew - 8:15 hrs
- Aunnalee - 8 hrs. Total hours 32.
- Barry -
Wed Aug 20, 2025
- Lost track of numbers from Tue and Wed - but if 90 by Thursday - did we do 57 over Tue & Wed? Way too high.
- Matthew - 8 hrs
- Aunnalee - 8 hrs
- Barry -
Tue Aug 19, 2025
- Matthew 5:45 -
- Alex - not here.
- Barry - arrived. 3 PM
- Aunnalee - 8 hr
Mon Aug 18, 2025
- Matthew, Aunnalee, Jacob - 8 hr x3 = 24 hrs/15 modules done today= 1.6. Same as Saturday? 3x instead of 1x. Jig issues - fixed.
- 27 total modules in 2 days. But there were 6 from before, so total is 33 done.
Sat Aug 16, 2025
Start of hangar walls.
- Total Alex - 42 hr
- Total Matthew - 23.5 hr
- 10-3 - Eric S - hr building Hangar walls
- Boys - Monday 6 hours x3
- Barry - 3 days - 6 hrs each
- Modules done today - MJ 1 hr - Barry, Eric for 6 hr, Matthew + Alex 3 hr - 19 hr tot , 12 modules - 1.6 hour per, no jig.
Sat Aug 9, 2025
- 4 hr Alex - 3 truss
- 4 hr Matthew - 3 truss
- 2 hr Conrad 1 truss
- MJ cutting OSB strips, + 1 row of Roof OSB in 30 min.
- Total Alex hrs 40.25
Fri Aug 8, 2025
- Alex and Matthew on trusses - 3 rows
- Was it 5.75 hrs
Thu Aug 7, 2025
- Doing mid section. One truss nailed in upside down. One not set 2' away from supporting truss.
- 8hr for the simmonses. Need pay, did you to Wed.
- Alex - 7.5hrs
Wed Aug 6, 2025
- Alex 6hr, 10-4:30, 1/2 hr lunch - 6 hr.
- Boyz - 5:30 hr from 10 to 6 with break
- Suzanne - couple hours for 5 trusses with the Family School Apprenticeship
Tue Aug 5, 2025
- MJ 3 headers 3 hours including one miscut has to be cut down second time.
- Alex 10:30 am start - 8.5 hrs.
- Simmonses - 10-6 with lunch - 7:30 hrs each
- Matthew - 4 PM to 8 - 4 hrs
Mon Aug 4, 2025
- MJ 1.5 hr for truss
- Alex - 8.5 hrs
- Matthew - 7 hours
Sat Aug 2, 2025
About 12 working people. Start 8 AM to 6:30 PM.
Fri Aug 1, 2025
- Pour - 8hr with Porter, Sam, and Parley. Alex 8 hr. Dean 5:30 hr. Charles 6 hr.
Thu
- Built 40 trusses, 16', and 16 trusses 24' - 56 total. Day total one per half hour + me as support - if count me . I was cutting strips and end pieces, mostly organizing tools and efficiency. With me counts as 35 minutes per truss, which is poor.
- Alex 7 hr.
- Boys 6.5 hr x3
Wed Jul 30, 2025
- Porter, Sam, and Parley - 6 hr each. Did 6 headers and then some.
Tue
- 7.5 hr x3.. Simmons boys 25 reinforces 24 ft trusses, about 5 hr, total of 7.5 hr with 17 more simple wall modules, me helping on wall.
- Matthew 8 reinf truss 4 hr