=Actual=  
Note that this budget includes equipment and materials mixed together
 
 
=Phase 1: Shop Roofing and Preparation=  
 
*4 [http://www.amazon.com/Milwaukee-2401-22-12-Volt-Li-Ion-Compact/dp/B000WI9CIG/ref=sr_1_1?s=hi&ie=UTF8&qid=1311881639&sr=1-1 Milwaukee cordless drills] – $407
*4 [http://www.amazon.com/Milwaukee-2401-22-12-Volt-Li-Ion-Compact/dp/B000WI9CIG/ref=sr_1_1?s=hi&ie=UTF8&qid=1311881639&sr=1-1 Milwaukee cordless drills] – $407
*Roof metal - 136 panels, 17' long (3' widths) - 108 for workshop, 22 for material shed, and 6 extra + flashing for clerestory + screws + flashing closure – $5871  
*Roof metal - 136 panels, 17' long (3' widths) - 108 for workshop, 22 for material shed, and 6 extra + flashing for clerestory + screws + flashing closure – $5871  
*2x6 lumber, 6.60 - total 396 pieces - $2802  
*2x6 lumber, 6.60 - total 396 pieces - $2802  
*Glue, #25 star driver bits, 3" star bit screws, 2 glue guns, furring strips, 2 tie downs – $299
*Glue, #25 star driver bits, 3" star bit screws, 2 glue guns, furring strips, 2 tie downs – $299
*Trailer rental for lumber – $47
*Trailer rental for lumber – $47
*Gravel for OSE Shop 2011 - 5000 sq ft of 6" deep plus 4x4x3' pillar bases - $2703
*Gravel for OSE Shop 2011 - 5000 sq ft of 6" deep plus 4x4x3' pillar bases - $2703
*Dimensional sawmill prototype 1 - check mailed directly to Sweiger - $10,000
=Phase 2 Foundations=
*Sep. 29, 2011 -Excavation and bulldozing, Workshop and HabLab, Duffy Reynolds Construction - $4k
*Oct. 3, 2011 - Construction rebar, Sweiger - $3968.60
*Oct. 3, 2011 - LifeTrac bucket prototype 1, Sweiger - $828
*Oct. 3, 2011 - LifeTrac tracks chain for 3 tractors - $1046.97
*Oct. 3, 2011 - metal, hydraulic coolers, welding supplies, 2 generators - $2786.39
*Oct. 4, 2011 - foundation pads concrete, Payless Concrete - $821.28
*Oct. 6, 2011 - HabLab step edge excavation correction - $437.50
*Oct. 8, 2011 - 2 soil pulverizer Prototype 3s complete minus motors, bearings, and chain - $4006.18
*Oct. 10, 2011 - mowing (280), raking (140), baling (220), 20 acres, for insulation - $640.00
*Oct. 13, 2011 - 30" and 13"sawblades for Dimensional Sawmill prototype I, teeth, wrench - $1062.95
*Oct. 14, 2011 - additional gravel for HabLab, 17 tons, Apac - $254.79
*Oct. 14, 2011 - 9 + 6 cu yds concrete pour for HabLab walls, kitchen, bathroom, Payless Concrete - $1910.43
*Oct. 14, 2011 - lumber for HabLab roof and framing - $2742.03
*Oct. 14, 2011 - foundation form lumber, HabLab - $210.03
*Oct. 14, 2011 - roof tiedown threaded rod and nuts, MoKan Fastener - $67.22
*Oct. 14, 2011 - 5 hard hats - $52.18
*Oct. 14, 2011 - PowerCube muffler studs and nuts - $57.54
*Total material cost: ~$15,000 so far
*Target budget for $5/sq.ft cost - $25,000
=Phase 3- Walls and Insulation=
*Oct. 20, 2011 - 4 of 55 lb bags of Borax for vermin protection of hay bales - [https://www.camdengrey.com/ $362]
*Oct. 20, 2011 - Bobcat rental for 1 month - $2254

Latest revision as of 16:09, 20 October 2011

Note that this budget includes equipment and materials mixed together


Phase 1: Shop Roofing and Preparation

  • Roof metal - 136 panels, 17' long (3' widths) - 108 for workshop, 22 for material shed, and 6 extra + flashing for clerestory + screws + flashing closure – $5871
  • 2x6 lumber, 6.60 - total 396 pieces - $2802
  • Glue, #25 star driver bits, 3" star bit screws, 2 glue guns, furring strips, 2 tie downs – $299
  • Trailer rental for lumber – $47
  • Gravel for OSE Shop 2011 - 5000 sq ft of 6" deep plus 4x4x3' pillar bases - $2703
  • Dimensional sawmill prototype 1 - check mailed directly to Sweiger - $10,000


Phase 2 Foundations

  • Sep. 29, 2011 -Excavation and bulldozing, Workshop and HabLab, Duffy Reynolds Construction - $4k
  • Oct. 3, 2011 - Construction rebar, Sweiger - $3968.60
  • Oct. 3, 2011 - LifeTrac bucket prototype 1, Sweiger - $828
  • Oct. 3, 2011 - LifeTrac tracks chain for 3 tractors - $1046.97
  • Oct. 3, 2011 - metal, hydraulic coolers, welding supplies, 2 generators - $2786.39
  • Oct. 4, 2011 - foundation pads concrete, Payless Concrete - $821.28
  • Oct. 6, 2011 - HabLab step edge excavation correction - $437.50
  • Oct. 8, 2011 - 2 soil pulverizer Prototype 3s complete minus motors, bearings, and chain - $4006.18
  • Oct. 10, 2011 - mowing (280), raking (140), baling (220), 20 acres, for insulation - $640.00
  • Oct. 13, 2011 - 30" and 13"sawblades for Dimensional Sawmill prototype I, teeth, wrench - $1062.95
  • Oct. 14, 2011 - additional gravel for HabLab, 17 tons, Apac - $254.79
  • Oct. 14, 2011 - 9 + 6 cu yds concrete pour for HabLab walls, kitchen, bathroom, Payless Concrete - $1910.43
  • Oct. 14, 2011 - lumber for HabLab roof and framing - $2742.03
  • Oct. 14, 2011 - foundation form lumber, HabLab - $210.03
  • Oct. 14, 2011 - roof tiedown threaded rod and nuts, MoKan Fastener - $67.22
  • Oct. 14, 2011 - 5 hard hats - $52.18
  • Oct. 14, 2011 - PowerCube muffler studs and nuts - $57.54
  • Total material cost: ~$15,000 so far
  • Target budget for $5/sq.ft cost - $25,000

Phase 3- Walls and Insulation

  • Oct. 20, 2011 - 4 of 55 lb bags of Borax for vermin protection of hay bales - $362
  • Oct. 20, 2011 - Bobcat rental for 1 month - $2254