Marcin Work Plan: Difference between revisions
Jump to navigation
Jump to search
(Created page with "*August **main milestone is moving far forward on Strategic Plan and Recruiting Process **Physical: finishing Sawmill Testing and Field report **Organizational: **Psychological: ...") |
|||
(4 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
=Six Months: Freestyle Gantt= | |||
<html><img src="https://docs.google.com/drawings/pub?id=1pAHjXvjQDjwoUb8D65U7J4LjyfxtoRhn5nUG0GDDy9Y&w=700&h=500"> | |||
</html> | |||
[https://docs.google.com/drawings/d/1pAHjXvjQDjwoUb8D65U7J4LjyfxtoRhn5nUG0GDDy9Y/edit edit] | |||
*August | *August | ||
**main milestone is moving far forward on Strategic Plan and Recruiting Process | **Big Picture goal: main milestone is moving far forward on Strategic Plan and initiating rigorous Recruiting Process | ||
**Physical: finishing Sawmill Testing and | **Physical: finishing Sawmill Testing, producing Field Report and blog post | ||
**Organizational: | **Organizational: | ||
**Psychological: | **Psychological: beginning waking up at the crack of dawn | ||
*September | *September | ||
**recruiting core effort; goal of 100+ applicants per position | **recruiting core effort; goal of 100+ applicants per position | ||
**Torch Table completion | **Torch Table completion | ||
**Successful Collaborative Production Run on CEB Press | **Successful Collaborative Production Run on CEB Press | ||
*October | |||
**Onboarding first Master Prototyper and Machine Designer | |||
*November | |||
** | |||
*December |
Latest revision as of 11:01, 21 August 2012
Six Months: Freestyle Gantt
- August
- Big Picture goal: main milestone is moving far forward on Strategic Plan and initiating rigorous Recruiting Process
- Physical: finishing Sawmill Testing, producing Field Report and blog post
- Organizational:
- Psychological: beginning waking up at the crack of dawn
- September
- recruiting core effort; goal of 100+ applicants per position
- Torch Table completion
- Successful Collaborative Production Run on CEB Press
- October
- Onboarding first Master Prototyper and Machine Designer
- November