=11th March, 2014= | |||
3D range of motion test for hydraulic cylinder. | |||
http://opensourceecology.org/wiki/Soil_Mixer_-_Opening_Mechanism_Module_-_Calculations | |||
http://opensourceecology.org/wiki/File:RangeOfMotion.png | |||
http://opensourceecology.org/wiki/Soil_Mixer_-_Opening_Mechanism_Module_-_Bill_of_Materials | |||
=11th March, 2014= | =11th March, 2014= | ||
https://www.youtube.com/watch?v=KjADHmrkFy4 | https://www.youtube.com/watch?v=KjADHmrkFy4 |
Revision as of 17:14, 12 March 2014
11th March, 2014
3D range of motion test for hydraulic cylinder.
http://opensourceecology.org/wiki/Soil_Mixer_-_Opening_Mechanism_Module_-_Calculations
http://opensourceecology.org/wiki/File:RangeOfMotion.png
http://opensourceecology.org/wiki/Soil_Mixer_-_Opening_Mechanism_Module_-_Bill_of_Materials
11th March, 2014
https://www.youtube.com/watch?v=KjADHmrkFy4
Tested different whitewash formula. it appeared that thick lime wash was less tolerant of some areas of the wall and was peeling back at some points after some time had passed. We applied a thin whitewash with the consistency of cream or milk at the end to different parts of the wall to see if we could avoid the peeling problem.
Drew the clamshell mechanism and hinge in sketch up for the Soil Mixer.
Sketchup in progress
File:SoilPulverizerV1s001.skp
10th March, 2014
Timelapse of wall painting- https://www.youtube.com/watch?v=o4bef_KFQts
Helped sketch designs for soil mixer.
Painted wall with Lauren and Cat. (timelapse video in progress)
Cooked thai style fried rice for dinner.
Commenced ideation for procedural animation of the GVCS in Houdini for documentation.
9th March, 2014
Append design Rationale - http://opensourceecology.org/wiki/Soil_Mixer_Construction_Set_Requirements
Laid hay over the ground to stop mud being moved along the path.