Line 5: | Line 5: | ||
*No insulation covers any wiring or plumbing work. | *No insulation covers any wiring or plumbing work. | ||
*Air test of water supply - leave a test port in water supply for air pressure testing or water pressure testing. | *Air test of water supply - leave a test port in water supply for air pressure testing or water pressure testing. | ||
*Smoke detectors are required on the electrical side - [https://www.cityofeasley.com/Rough-In%20Inspection%20Checklist.pdf] |
Revision as of 15:49, 1 June 2021
- The rough inspection should be performed before the insulation is installed. This is not stated as a requirement, but a suggestion here. [1]
- Rough-in inspection can also occur after insulation is in, but it may be more difficult to perform inspection. [2]
OSE Case
- No insulation covers any wiring or plumbing work.
- Air test of water supply - leave a test port in water supply for air pressure testing or water pressure testing.
- Smoke detectors are required on the electrical side - [3]