'''Rough-in inspections include plumbing, electrical, and framing:'''
=Electrical=
*includes wiring and breakers
*Includes ground conductor
*Includes all enclosures - breaker boxes, outlet boxes
*''Switches, receptacles and fixtures should not be installed at the rough-in.''
=Framing=
=Framing=
*Includes both interior and exterior walls, load bearing or not. Inspection is done after all rough-in plumbing and electrical, and ducting is in place.
*Includes both interior and exterior walls, load bearing or not. Inspection is done after all rough-in plumbing and electrical, and ducting is in place.

Revision as of 04:34, 10 January 2022

Document for Alaska - [1]

Site Plan

  • this is the first inspection

Foundation

Rough-in inspections include plumbing, electrical, and framing:

Electrical

  • includes wiring and breakers
  • Includes ground conductor
  • Includes all enclosures - breaker boxes, outlet boxes
  • Switches, receptacles and fixtures should not be installed at the rough-in.

Framing

  • Includes both interior and exterior walls, load bearing or not. Inspection is done after all rough-in plumbing and electrical, and ducting is in place.