Seed Eco-Home 4 Data Collection: Difference between revisions

From Open Source Ecology
Jump to navigation Jump to search
Line 3: Line 3:


=Framing=
=Framing=
*48 minutes to do front top garage module (for triple strap tiedown)
*48 minutes to do front top garage module (for triple strap tiedown). Using already cut members. Most of the lumber was available, did not need to cut any.
*1 hr 7 minutes to do 3 modules, front garage top, simple. Most wood was already cut. Adding cutting would add 5 minutes to time per module? See [https://photos.app.goo.gl/zgHjXnvUrL2rGCwYA pictures]. Siple modules have 9 members.
*1 hr 7 minutes to do 3 modules, front garage top, simple. Blocking and bottom/top was already cut, I had to cut verticals. Adding cutting would add 5 minutes to time per module? See [https://photos.app.goo.gl/zgHjXnvUrL2rGCwYA pictures]. Simple modules have 9 members.
*50 minutes demo for one full simple 9' module build, including detailed quality control with unruly wood - during workshop.
*50 minutes demo for one full simple 9' module build, including detailed quality control with unruly wood - during workshop.



Revision as of 18:17, 3 January 2023

People

Framing

  • 48 minutes to do front top garage module (for triple strap tiedown). Using already cut members. Most of the lumber was available, did not need to cut any.
  • 1 hr 7 minutes to do 3 modules, front garage top, simple. Blocking and bottom/top was already cut, I had to cut verticals. Adding cutting would add 5 minutes to time per module? See pictures. Simple modules have 9 members.
  • 50 minutes demo for one full simple 9' module build, including detailed quality control with unruly wood - during workshop.

Tasks

  • Concrete summary - 27 prep, 15 pour prep (8 am till 1 with 3) + 6 hr pour (3 people 2 hrs until scree) + 5 hr floating in extremely slow drying time. Total concrete time = 53 hr. This was 1104 sf compared to 500 sf last time at 42 hours, so scaling is favorable: 1.7 times faster than the 500 sf.
  • Wed Dec 7 - 14 hrs? Casey and Aidan on Bobcats from noon to 6, Aidan till 8 PM. I set up the site for 3 hours, talked to neighbors, packed up portopotty.
  • Tue Dec 6 - 19.5 hr till finish of pour with 3 people from 8 to 2:30 PM. Got gravel level, did poly, rebar, chairs, mudsill anchors recessed - then I until 8 PM floating and power trowel. Aidan was there outside of 2 hours cleaning up. Packing up trailer to travel to Savannah until 9 PM. Total work - 5 hrs power trowel, and 3 other (Aidan) + 2 hr packing. Total of 27.5 hr total concrete-related.
  • Mon Dec 5, 2022 - 12 hrs to plumbing, gravel spread. Insulation on forms. + 3 for Brent on plumbing etc.
  • Sun Dec 4, 2022 -12 hrs to forms largely done, minus entry to garage


  • Friday Dec 2, 2022 - Laser level and evening high spots - about 25 minutes? Meter reading - . All together today - 5 hrs including selecting final location, calculating diagonals, figuring out foundation detail, starting micro excavator work. Bulk of time - deciding on proper location of house.
  • Thu Dec 1 -Smoothing - 1044.4 - 1045.5 - 1.1 hrs.
  • Dig time - 1042.1-1044.4 - 2.3 hrs. Finishing of bulk digging.
  • Dig time - 4:10 on Sunday. Bulk of the diggin. Key is to get into mindless flow, which is possible with ample soil, and is definitely easier if the soil is not rock hard like clay. 1038.0-1042.1
  • Scrape time for grass for 70x50 area - 2 hrs. Start hour meter = 1036.0