Sat Feb 10 2023 Notes: Difference between revisions

From Open Source Ecology
Jump to navigation Jump to search
No edit summary
No edit summary
Line 1: Line 1:
'''Build Items:'''
'''Build Items:'''
*Door installation
#Exterior trim
#Door installation
#Siding
 
'''Done'''
#Foundation trim - 8 hr + 4 hrs = 11 hrs + 20 min rivets
*Stairs
*Stairs
*Landing
*Landing
Line 15: Line 20:
*Heat pump
*Heat pump
*Trellis
*Trellis
*Foundation trim
 
*Siding
 
*Exterior trim
 
*Interior frame, electrical, plumbing
*Interior frame, electrical, plumbing
*Beadboard
*Beadboard

Revision as of 16:18, 18 February 2023

Build Items:

  1. Exterior trim
  2. Door installation
  3. Siding

Done

  1. Foundation trim - 8 hr + 4 hrs = 11 hrs + 20 min rivets
  • Stairs
  • Landing
  • Canopy
  • Behind tub and behind stair sheet and insulation
  • Front porch
  • 2nd floor ceiling insulation
  • 2nd floor ceiling
  • Interior sill plates sketches
  • Sill plates (none on 2nd)
  • Power center
  • Inverter
  • PV
  • Heat pump
  • Trellis


  • Interior frame, electrical, plumbing
  • Beadboard
  • Paint interior
  • Kitchen cabinets
  • Bathroom
  • Finish floor
  • Driveway
  • Sewer
  • Water
  • Power connection
  • Landscaping - tree spade etc

Design Items:

  • Garage deck
  • Build order doc - walls/insul/landing/stair/etc
  • Inverter
  • Power center and trenching
  • Canopy
  • Trellis
  • Overall garage top build order doc