Solar Hydrogen Challenge: Difference between revisions

From Open Source Ecology
Jump to navigation Jump to search
Line 5: Line 5:
*For 10kg/hr - cost is about $150k capex, so if this gives 60k hours or 600k kg (600 tons) - return is $1.2M at $150k capex, closer to 10x ROI. [https://chatgpt.com/share/69532e9b-d73c-8010-b3f1-dfb737507341]
*For 10kg/hr - cost is about $150k capex, so if this gives 60k hours or 600k kg (600 tons) - return is $1.2M at $150k capex, closer to 10x ROI. [https://chatgpt.com/share/69532e9b-d73c-8010-b3f1-dfb737507341]
**Separator is only 10% capex. [https://chatgpt.com/share/69532e9b-d73c-8010-b3f1-dfb737507341]
**Separator is only 10% capex. [https://chatgpt.com/share/69532e9b-d73c-8010-b3f1-dfb737507341]
**If we go open source, we can lower cost so separator is 50% capex. Capex would then be $30k in the zero marginal cost scenario.
**If we go open source, we can lower cost so separator is 50% capex. Capex would then be $30k in the zero marginal cost scenario. That will take time.
**If off the shelf $150k capex - then payback is 150000/240= 625 days. Now we are talking.
**Technical challenge is there.


=Hydrogen Booster Sourcing=
=Hydrogen Booster Sourcing=

Revision as of 02:02, 30 December 2025

Alkaline Electrolyzer Sourcing

  • 1kg/hr system takes a 60kW PV system for the magical 60kWhr/kg yield. But - separating membrane there can be $5-10k. Costs $40k.
    • This system produces 60 tons over lifetime - or $120k worth of hydrogen - or ROI=3x.
  • Make your own plates - nickel coating mild steel - 50 lb nickel for 1 kg/hr - and 200 lb salts. Cost several hundred dollars for 1 kg/hr.
  • For 10kg/hr - cost is about $150k capex, so if this gives 60k hours or 600k kg (600 tons) - return is $1.2M at $150k capex, closer to 10x ROI. [1]
    • Separator is only 10% capex. [2]
    • If we go open source, we can lower cost so separator is 50% capex. Capex would then be $30k in the zero marginal cost scenario. That will take time.
    • If off the shelf $150k capex - then payback is 150000/240= 625 days. Now we are talking.
    • Technical challenge is there.

Hydrogen Booster Sourcing

500 Bar Tanks

Hydrogen Engine Conversion