Factor e Farm Infrastructure Buildout 2011: Difference between revisions
No edit summary |
|||
Line 7: | Line 7: | ||
We have a $60k donation offer for building the infrastructure. The tactical plan is: | We have a $60k donation offer for building the infrastructure. The tactical plan is: | ||
#Build post-and-beam covered space with metal roofing as in the workshop addition. | #Build post-and-beam covered space with metal roofing as in the workshop addition - [http://blog.opensourceecology.org/2011/04/workshop-addition/]. | ||
#Build on level area already marked out last year; lay 6" of gravel | #Build on level area already marked out last year; lay 6" of gravel for leveling area | ||
#Auger post-and-beam 4x4 lumber holes, embed in concrete base | |||
# | |||
=Materials= | |||
*$3.5k - Thermaclear glazing ($2/sq ft for 1750 sq ft) | *$3.5k - Thermaclear glazing ($2/sq ft for 1750 sq ft) | ||
*$3k - Gravel for foundations- 12 truck loads, $250 each | *$3k - Gravel for foundations- 12 truck loads, $250 each | ||
*$5k - construction lumber | |||
*$2k - kitchen outfitting | |||
*$3k - bathroom outfitting | |||
*$1k - Fuel | *$1k - Fuel | ||
*$2k - Doors, windows | *$2k - Doors, windows | ||
Line 28: | Line 33: | ||
*$1k - cement mixer build | *$1k - cement mixer build | ||
*$1k - trencher build | *$1k - trencher build | ||
*$ | *$2k - square baler purchase | ||
*$ | *$750 - sickle bar purchase | ||
*$ | *$750 - hay rake purchase | ||
*$4k - fully automatic CEB press build (2 total will be available at Factor e Farm for the construction season) | *$4k - fully automatic CEB press build (2 total will be available at Factor e Farm for the construction season) | ||
*$5.5k - 3 more Power Cubes to support 2 tractors at 54 hp each and 2 CEB presses | *$5.5k - 3 more Power Cubes to support 2 tractors at 54 hp each and 2 CEB presses | ||
*$3k - if time allows, build sawmill for cutting our own lumber. | |||
=Additional Workshop Equipment= | |||
See [[Factor e Farm Production Facility]] | See [[Factor e Farm Production Facility]] |
Revision as of 18:13, 1 July 2011
Introduction
2011 marks the buildout of Factor e Farm for the purpose of absorbing 6-12 people full time with comfortable accommodations and work space. We are planning on using the CEB press and strawbale insulation as the core of the built environment, as an application of Modular CEB Construction. The planned infrastructure buildout includes 6 superinsulated studios, 6 more 3-season studios, common kitchen, common shower/bathroom, supporting electrical power and internet infrastructure, and a 3000 square foot workshop addition. The return on investment goal is $20-60k/month bootstrap funding generated as a result of production/training operations, where all cash is funneled into continued, rapid GVCS development.
Strategy
We have a $60k donation offer for building the infrastructure. The tactical plan is:
- Build post-and-beam covered space with metal roofing as in the workshop addition - [1].
- Build on level area already marked out last year; lay 6" of gravel for leveling area
- Auger post-and-beam 4x4 lumber holes, embed in concrete base
Materials
- $3.5k - Thermaclear glazing ($2/sq ft for 1750 sq ft)
- $3k - Gravel for foundations- 12 truck loads, $250 each
- $5k - construction lumber
- $2k - kitchen outfitting
- $3k - bathroom outfitting
- $1k - Fuel
- $2k - Doors, windows
- $1k - fasteners
- $5k - Metal roofing
- $5k - cement for foundations
- $2k - electrical supplies
- $1k - misc power tools
Total - $22k
Equipment
- $1k - cement mixer build
- $1k - trencher build
- $2k - square baler purchase
- $750 - sickle bar purchase
- $750 - hay rake purchase
- $4k - fully automatic CEB press build (2 total will be available at Factor e Farm for the construction season)
- $5.5k - 3 more Power Cubes to support 2 tractors at 54 hp each and 2 CEB presses
- $3k - if time allows, build sawmill for cutting our own lumber.