Crack Of Dawn Meetings: Difference between revisions
Jump to navigation
Jump to search
Tom Griffing (talk | contribs) No edit summary |
Tom Griffing (talk | contribs) No edit summary |
||
Line 8: | Line 8: | ||
* Discussed documentation efforts for Power Cube and CEB press. Tom said the biggest delays were in graphics and distractions. | * Discussed documentation efforts for Power Cube and CEB press. Tom said the biggest delays were in graphics and distractions. | ||
* Discussed to do tasks: | * Discussed to do tasks: | ||
Tom - test electronics | ** Tom - test electronics | ||
Shonda - investigate milling machines for purchase | ** Shonda - investigate milling machines for purchase | ||
Briana - finalize CEB press | ** Briana - finalize CEB press | ||
Everyone - Help with new structure, adding extenders to roof | ** Everyone - Help with new structure, adding extenders to roof |
Revision as of 21:57, 22 August 2011
Sunday, August 22
- The first part of meeting addressed wiki and that everyone needs to be maintaining log entries for their participation.
- The discussion then went into the tasks to be performed.
- Then discussed immediate to do list - the first task was to work on the roof for the new shop space.
Monday, August 23
- Discussed everyone's access to the wiki Logs - some were still lacking and followed up on getting everyone's log updated.
- Discussed documentation efforts for Power Cube and CEB press. Tom said the biggest delays were in graphics and distractions.
- Discussed to do tasks:
- Tom - test electronics
- Shonda - investigate milling machines for purchase
- Briana - finalize CEB press
- Everyone - Help with new structure, adding extenders to roof