Jan 26th: Complete boiler research: Feed Pump, Montotube coil winding jig, safety valve. | *Jan 26th: Complete boiler research: Feed Pump, Montotube coil winding jig, safety valve. | ||
Finish brick laying in shop. Finish steam engine proposal. | Finish brick laying in shop. Finish steam engine proposal. | ||
Misc: Debit card activation, skype account, Explorer showing. | Misc: Debit card activation, skype account, Explorer showing. | ||
Time Organization program: Need linked in program. | Time Organization program: Need linked in program. | ||
Jan 27th: Complete Steam pump and Lathe BOM post and post steam engine proposal. | |||
*Jan 27th: Complete Steam pump and Lathe BOM post and post steam engine proposal. | |||
Frame inside of Shop kitchen. | Frame inside of Shop kitchen. | ||
Jan 28th: Get quote of materials from Sweigers: | |||
*Jan 28th: Get quote of materials from Sweigers: | |||
Insulate shop and get sheet rock. | Insulate shop and get sheet rock. | ||
Jan 29th: Order steam engine and lathe materials. | *Jan 29th: Order steam engine and lathe materials. | ||
Post final dwgs of mechanical engine, boiler, and layout. | Post final dwgs of mechanical engine, boiler, and layout. | ||
Jan 30th: Research steam engine solenoid specs, post and locate. | |||
*Jan 30th: Research steam engine solenoid specs, post and locate. | |||
Sheet rock shop space, drill in shower outlet fire boiler. | Sheet rock shop space, drill in shower outlet fire boiler. | ||
*Jan 30th: Work on shop try to get liveable cookeable space. | |||
Feb | *Feb 1st: Rest | ||
1 week Boiler and auxilaries, safety valve, feed pumps, draft control. | *Feb 2nd: Begin steam engine work upon reciveing materials: 1 week Boiler and auxilaries, safety valve, feed pumps, draft control. | ||
2nd week February: | *2nd week February: Engine construction. Bore cylinder set piston rings, assemble stuffing box, | ||
Engine construction. Bore cylinder set piston rings, assemble stuffing box, | |||
3rd week of February: | *3rd week of February: Lower Crank Assembly, fire up system possibly by the end of the week. | ||
Lower Crank Assembly, fire up system possibly by the end of the week. | |||
[[Category:Planning]] | [[Category:Planning]] |
Revision as of 01:35, 26 January 2009
- Jan 26th: Complete boiler research: Feed Pump, Montotube coil winding jig, safety valve.
Finish brick laying in shop. Finish steam engine proposal. Misc: Debit card activation, skype account, Explorer showing. Time Organization program: Need linked in program.
- Jan 27th: Complete Steam pump and Lathe BOM post and post steam engine proposal.
Frame inside of Shop kitchen.
- Jan 28th: Get quote of materials from Sweigers:
Insulate shop and get sheet rock.
- Jan 29th: Order steam engine and lathe materials.
Post final dwgs of mechanical engine, boiler, and layout.
- Jan 30th: Research steam engine solenoid specs, post and locate.
Sheet rock shop space, drill in shower outlet fire boiler.
- Jan 30th: Work on shop try to get liveable cookeable space.
- Feb 1st: Rest
- Feb 2nd: Begin steam engine work upon reciveing materials: 1 week Boiler and auxilaries, safety valve, feed pumps, draft control.
- 2nd week February: Engine construction. Bore cylinder set piston rings, assemble stuffing box,
- 3rd week of February: Lower Crank Assembly, fire up system possibly by the end of the week.