  • Documented problems encountered during Lasersaur Exterior Panel Installation
  • Started Workshop reorganize and fixed some power tool plugs and extension cord ends.
  • Worked with a team to reassemble the CEB Press. Learned it is important to have a CAD model that matches the actual model. Also good to replace nuts and washers onto corresponding bolts while disassembling in order to simplify reassembly.

Mon. 2 Jun 2014

Sat. 31 May 2014

  • Finalized prep for OSE
  • Installed software recommended in DPV Offer Letter