Door Requirement: Difference between revisions

From Open Source Ecology
Jump to navigation Jump to search
(Created page with "*Door is only 7' high (same as wall) because of the height requirement of ceiling. *Door must be integrated into 1' thick CEB wall with stucco and 2" EPS insulation. *Bond bea...")
 
No edit summary
Line 2: Line 2:
*Door must be integrated into 1' thick CEB wall with stucco and 2" EPS insulation.
*Door must be integrated into 1' thick CEB wall with stucco and 2" EPS insulation.
*Bond beam is directly above it.
*Bond beam is directly above it.
*Finishing detail involves direct transition from door frame to stucco metal lath
*Finishing detail involves direct transition from door frame to stucco metal lath without need for any other trim

Revision as of 01:34, 28 August 2014

  • Door is only 7' high (same as wall) because of the height requirement of ceiling.
  • Door must be integrated into 1' thick CEB wall with stucco and 2" EPS insulation.
  • Bond beam is directly above it.
  • Finishing detail involves direct transition from door frame to stucco metal lath without need for any other trim