Current | =Current Priorities= | ||
*Finishing complete blueprints for [[CEB Press]]. Releasing manual build and CNC build versions - Prototype 4 and 6 - see [[CEB Press Genealogy]]. | *Finishing complete blueprints for [[CEB Press]]. Releasing manual build and CNC build versions - Prototype 4 and 6 - see [[CEB Press Genealogy]]. | ||
*Goal is to release complete documentation where a person can build the CEB Press, either on their own, or by instructing a local fabricator in the process | |||
:*This includes the main challenge of quality control | |||
:*OSE will generate sample production contract/ QC protocols for fabricators | |||
:*OSE will organize a one day CEB Production Intro Workshop for people interested in building the machine, either for themselves of for sale | |||
:*Goal: distribute production of 100-1000 machines within 12 months of full publishing. | |||
=Team= | =Team= |
Revision as of 19:00, 27 February 2015
Current Priorities
- Finishing complete blueprints for CEB Press. Releasing manual build and CNC build versions - Prototype 4 and 6 - see CEB Press Genealogy.
- Goal is to release complete documentation where a person can build the CEB Press, either on their own, or by instructing a local fabricator in the process
- This includes the main challenge of quality control
- OSE will generate sample production contract/ QC protocols for fabricators
- OSE will organize a one day CEB Production Intro Workshop for people interested in building the machine, either for themselves of for sale
- Goal: distribute production of 100-1000 machines within 12 months of full publishing.
Team
- Marcin Jakubowski
- John Dilday
- Matt Richardson