*Wires cable-stapled to studs
*Wires cable-stapled to studs
*Wires 1.25" below surface, or need protective metal plates. [https://www.process.st/checklist/electrical-inspection-checklist-residential-rough-inspection-general/]
*Wires 1.25" below surface, or need protective metal plates. [https://www.process.st/checklist/electrical-inspection-checklist-residential-rough-inspection-general/]
*Check appropriate conductor fill of boxes. [https://www.ecmweb.com/national-electrical-code/code-basics/article/20886012/box-fill-calculations]

Revision as of 15:52, 28 May 2021

  • How to pass - [1]

Guidelines

  • No devices are installed, just wires and boxes
  • PLug holes between floors with insulation of fire block foam to prevent fire spread [2]
  • All wires have wire nuts on them at rough-in
  • Wires cable-stapled to studs
  • Wires 1.25" below surface, or need protective metal plates. [3]
  • Check appropriate conductor fill of boxes. [4]