*The rough inspection should be performed before the insulation is installed. This is not stated as a requirement, but a suggestion here. [https://www.bartowcountyga.gov/Typical%20Order%20of%20Inspections_06-17-16.pdf]
*The rough inspection should be performed before the insulation is installed. This is not stated as a requirement, but a suggestion here. [https://www.bartowcountyga.gov/Typical%20Order%20of%20Inspections_06-17-16.pdf]
*Rough-in inspection can also occur after insulation is in, but it may be more difficult to perform inspection. [https://inspectusa.com/blog/pre-drywall-inspection-and-scheduling-inspection/#:~:text=A%20Pre%2Ddrywall%20inspection%20should,IN%E2%80%9D%20portion%20of%20the%20project.&text=When%20everything%20is%20100%25%20completed,signed%20off%2C%20ready%20for%20insulation.]
*Rough-in inspection can also occur after insulation is in, but it may be more difficult to perform inspection. [https://inspectusa.com/blog/pre-drywall-inspection-and-scheduling-inspection/#:~:text=A%20Pre%2Ddrywall%20inspection%20should,IN%E2%80%9D%20portion%20of%20the%20project.&text=When%20everything%20is%20100%25%20completed,signed%20off%2C%20ready%20for%20insulation.]
=OSE Case=
*No insulation covers any wiring or plumbing work.

Revision as of 15:42, 1 June 2021

  • The rough inspection should be performed before the insulation is installed. This is not stated as a requirement, but a suggestion here. [1]
  • Rough-in inspection can also occur after insulation is in, but it may be more difficult to perform inspection. [2]

OSE Case

  • No insulation covers any wiring or plumbing work.