Under Construction Phase Inspections: Difference between revisions
Jump to navigation
Jump to search
Line 14: | Line 14: | ||
*Includes all enclosures - breaker boxes, outlet boxes | *Includes all enclosures - breaker boxes, outlet boxes | ||
*''Switches, receptacles and fixtures should not be installed at the rough-in.'' | *''Switches, receptacles and fixtures should not be installed at the rough-in.'' | ||
=Plumbing and Mechanical= | |||
*Prior to any enclosure, plumbing is inspected | |||
*Includes water, drain, waste, and vents | |||
*Includes HVAC vents; range, dryer and bathroom vents; water heater and venting; others. If water heater is not fuel-fired, | |||
=Framing= | =Framing= | ||
*Includes both interior and exterior walls, load bearing or not. Inspection is done after all rough-in plumbing and electrical, and ducting is in place. | *Includes both interior and exterior walls, load bearing or not. Inspection is done after all rough-in plumbing and electrical, and ducting is in place. |
Revision as of 04:40, 10 January 2022
Document for Alaska - [1]
Site Plan
- this is the first inspection
Foundation
Rough-in inspections include plumbing, electrical, and framing:
Electrical
- includes wiring and breakers
- Includes ground conductor
- Includes all enclosures - breaker boxes, outlet boxes
- Switches, receptacles and fixtures should not be installed at the rough-in.
Plumbing and Mechanical
- Prior to any enclosure, plumbing is inspected
- Includes water, drain, waste, and vents
- Includes HVAC vents; range, dryer and bathroom vents; water heater and venting; others. If water heater is not fuel-fired,
Framing
- Includes both interior and exterior walls, load bearing or not. Inspection is done after all rough-in plumbing and electrical, and ducting is in place.