Under Construction Phase Inspections: Difference between revisions

From Open Source Ecology
Jump to navigation Jump to search
No edit summary
Line 19: Line 19:
*Includes house wrap
*Includes house wrap


=Electrical=
==Electrical==
*includes wiring and breakers
*includes wiring and breakers
*Includes ground conductor
*Includes ground conductor
Line 25: Line 25:
*''Switches, receptacles and fixtures should not be installed at the rough-in.''
*''Switches, receptacles and fixtures should not be installed at the rough-in.''


=Plumbing and Mechanical=
==Plumbing and Mechanical==
*Prior to any enclosure, plumbing is inspected
*Prior to any enclosure, plumbing is inspected
*Includes water, drain, waste, and vents
*Includes water, drain, waste, and vents
*Includes HVAC vents; range, dryer and bathroom vents; water heater and venting; others. If water heater is not fuel-fired,
*Includes HVAC vents; range, dryer and bathroom vents; water heater and venting; others. If water heater is not fuel-fired,


=Framing=
==Framing==
*Includes both interior and exterior walls, load bearing or not. Inspection is done after all rough-in plumbing and electrical, and ducting is in place.
*Includes both interior and exterior walls, load bearing or not. Inspection is done after all rough-in plumbing and electrical, and ducting is in place.

Revision as of 04:49, 10 January 2022

References

  • Document for Alaska - [1]
  • Inspection Descriptions Florida - [2]
  • Guidelines Georgia - [3]

Site Plan

  • this is the first inspection

Grading Inspection

  • This is inspected in Georgia.

Foundation

  • Slab inspection happens before pouring
  • Plumbing under-slab may be inspected prior to covering

Complete Rough

  • Rough-in inspections include plumbing, electrical, and framing:
  • Includes house wrap

Electrical

  • includes wiring and breakers
  • Includes ground conductor
  • Includes all enclosures - breaker boxes, outlet boxes
  • Switches, receptacles and fixtures should not be installed at the rough-in.

Plumbing and Mechanical

  • Prior to any enclosure, plumbing is inspected
  • Includes water, drain, waste, and vents
  • Includes HVAC vents; range, dryer and bathroom vents; water heater and venting; others. If water heater is not fuel-fired,

Framing

  • Includes both interior and exterior walls, load bearing or not. Inspection is done after all rough-in plumbing and electrical, and ducting is in place.