*Guidelines Georgia - [https://cms2files.revize.com/bartowga/Typical%20Order%20of%20Inspections_06-17-16.pdf]
*Guidelines Georgia - [https://cms2files.revize.com/bartowga/Typical%20Order%20of%20Inspections_06-17-16.pdf]
*South Carolina - [https://www.cityofeasley.com/Rough-In%20Inspection%20Checklist.pdf]
*South Carolina - [https://www.cityofeasley.com/Rough-In%20Inspection%20Checklist.pdf]
==Specifics==
*Smoke alarms required [https://house.mo.gov/billtracking/bills101/biltxt/intro/HB2429I.htm#:~:text=(3)%20In%20all%20newly%20constructed,equipped%20with%20a%20battery%20backup.]


=Site Plan=
=Site Plan=

Revision as of 05:01, 10 January 2022

References

  • Document for Alaska - [1]
  • Inspection Descriptions Florida - [2]
  • Guidelines Georgia - [3]
  • South Carolina - [4]

Specifics

  • Smoke alarms required [5]

Site Plan

  • this is the first inspection

Grading Inspection

  • This is inspected in Georgia.

Foundation

  • Slab inspection happens before pouring
  • Plumbing under-slab may be inspected prior to covering

Complete Rough

  • Rough-in inspections include plumbing, electrical, and framing:
  • Includes house wrap

Electrical

  • includes wiring and breakers
  • Includes ground conductor
  • Includes all enclosures - breaker boxes, outlet boxes
  • Switches, receptacles and fixtures should not be installed at the rough-in.

Plumbing and Mechanical

  • Prior to any enclosure, plumbing is inspected
  • Includes water, drain, waste, and vents
  • Includes HVAC vents; range, dryer and bathroom vents; water heater and venting; others. If water heater is not fuel-fired,

Framing

  • Includes both interior and exterior walls, load bearing or not. Inspection is done after all rough-in plumbing and electrical, and ducting is in place.

Insulation

  • This follows rough-in - and is prior to walls being covered

Final Inspection

Schedule this when the building is ready for occupancy. May include:

  • Building Final - such as wall covering
  • Landscape Final
  • Electrical Final -
  • Plumbing Final
  • Mechanical Final
  • Gas Final