Under Construction Phase Inspections: Difference between revisions
Jump to navigation
Jump to search
Line 8: | Line 8: | ||
==Specifics== | ==Specifics== | ||
*Smoke alarms required [https://house.mo.gov/billtracking/bills101/biltxt/intro/HB2429I.htm#:~:text=(3)%20In%20all%20newly%20constructed,equipped%20with%20a%20battery%20backup.] | *Smoke alarms required [https://house.mo.gov/billtracking/bills101/biltxt/intro/HB2429I.htm#:~:text=(3)%20In%20all%20newly%20constructed,equipped%20with%20a%20battery%20backup.] | ||
*Temp power pole - gen or off-grid is fine - [https://www.wpowerproducts.com/news/how-construction-sites-get-power/#:~:text=Generators%20can%20be%20used%20to,that%20needs%20electricity%20to%20operate.] | |||
=Site Plan= | =Site Plan= |
Revision as of 05:05, 10 January 2022
References
- Document for Alaska - [1]
- Inspection Descriptions Florida - [2]
- Guidelines Georgia - [3]
- South Carolina - [4]
Specifics
Site Plan
- this is the first inspection
Grading Inspection
- This is inspected in Georgia.
Foundation
- Slab inspection happens before pouring
- Plumbing under-slab may be inspected prior to covering
Complete Rough
- Rough-in inspections include plumbing, electrical, and framing:
- Includes house wrap
Electrical
- includes wiring and breakers
- Includes ground conductor
- Includes all enclosures - breaker boxes, outlet boxes
- Switches, receptacles and fixtures should not be installed at the rough-in.
Plumbing and Mechanical
- Prior to any enclosure, plumbing is inspected
- Includes water, drain, waste, and vents
- Includes HVAC vents; range, dryer and bathroom vents; water heater and venting; others. If water heater is not fuel-fired,
Framing
- Includes both interior and exterior walls, load bearing or not. Inspection is done after all rough-in plumbing and electrical, and ducting is in place.
Insulation
- This follows rough-in - and is prior to walls being covered
Final Inspection
Schedule this when the building is ready for occupancy. May include:
- Building Final - such as wall covering
- Landscape Final
- Electrical Final -
- Plumbing Final
- Mechanical Final
- Gas Final