Latest revision as of 18:22, 6 December 2024
- Key - preparation an preparation. Even floor - https://www.youtube.com/watch?v=lDEJhqMcgcQ
- Crew of 2 - 750 sf/day. By this, 32 hours min.
- 2-3 days for crew of 2 for 1000 sf [1]. This is 160 sf/day conservative, must include prep.