Max Log: Difference between revisions
Jump to navigation
Jump to search
No edit summary |
No edit summary |
||
| Line 6: | Line 6: | ||
{{Timelog|Max2}} | {{Timelog|Max2}} | ||
=Sat Nov 1, 2025= | |||
Morning: 10:00am-12:00pm | |||
* Installed flashing tape on both sliding doors | |||
[[File:Sliding doors flashing.jpg|thumb|left|Sliding door flashing tape]] | |||
* Built back veranda walls | |||
[[File:Back porch wall frames.jpg|thumb|left|Back veranda wall frames]] | |||
[[File:Back porch wall siding.jpg|thumb|left|Back veranda with wall siding installed]] | |||
Lunch: - | |||
Afternoon: 12:00pm-4:30pm | |||
* Leveled, positioned, and fixed front porch beneath sliding doors | |||
[[File:Back porch installed.jpg|thumb|left|Back veranda installed]] | |||
=Fri Oct 31, 2025= | =Fri Oct 31, 2025= | ||
| Line 13: | Line 35: | ||
* Finished 2nd window installation | * Finished 2nd window installation | ||
* | [[File:Window tar seal.jpg|thumb|left|Window sealed with tar tape]] | ||
* Build back veranda frame and installed planks | |||
[[File:Back porch frame.jpg|thumb|left|Back porch frame]] | |||
[[File:Back porch planks.jpg|thumb|left|Back veranda frame with planks installed]] | |||
Lunch: 2pm-3:35pm | Lunch: 2pm-3:35pm | ||
| Line 55: | Line 85: | ||
[[File:Window holes.jpg|thumb|Cut window holes]] | [[File:Window holes.jpg|thumb|Cut window holes]] | ||
* Installed flashing tar tape | * Installed flashing tar tape on both window frames | ||
[[File:Window flashing tape.jpg|thumb|Window flashing tape]] | [[File:Window flashing tape.jpg|thumb|Window flashing tape]] | ||
Revision as of 04:55, 2 November 2025
Build Pictures
- Upload - [1]
Time Log
Write down morning work done, lunch time, and afternoon work done.
Sat Nov 1, 2025
Morning: 10:00am-12:00pm
- Installed flashing tape on both sliding doors
- Built back veranda walls
Lunch: -
Afternoon: 12:00pm-4:30pm
- Leveled, positioned, and fixed front porch beneath sliding doors
Fri Oct 31, 2025
Morning: 10:25am-2pm
- Finished 2nd window installation
- Build back veranda frame and installed planks
Lunch: 2pm-3:35pm
Afternoon: 3:35pm-7pm
- Finished back veranda deck
- Started back veranda wall frames
- Screwed in 2nd rear veranda door frame
Thu Oct 30, 2025
Morning: 10:00am-12:00pm
- Trimmed PV runners
- Fixed up PV runner cap 2x4 on the 3rd module
- Folded up roof membrane at the south side to fit with PV runner cap 2x4s
- Installed some 1x6 roof trim
Lunch: -
Afternoon: 12:00pm-6:45pm
- Installed siding
- Cut opening for east side windows
- Installed flashing tar tape on both window frames
- Installed first window
- Started installation of second window
Wed Oct 29, 2025
Morning: 10:10am-12:15pm
- Installed PV panels
Lunch: 12:15pm-1:40pm
Afternoon: 1:40pm-7pm
- Finished installing PV panels
- Trimmed roof membrane on east side of building to fit trim boards
- Started installing trim boards on roof
Tue Oct 28, 2025
Morning: 10:05am-12:45pm
- Installed 2nd sliding door handle/lock and adjusted roller (~5min total)
- Put up R38 fiberglass insulation into the ceiling, covered about 5 rows
Lunch: 12:45pm-1:45pm
Afternoon: 1:45pm-5:15pm
- Sealed cracks & gaps between wall modules & rafters/taper with spray foam
- Finished ceiling insulation in the first 2 house modules
- Started insulating wall modules in house module 1 with R19 fiberglass
- Started taking off some of the floor level OSB strips to fill in gaps behind them with spray foam (in house module 3)
Mon Oct 27, 2025
Morning: 10:05am-2:30pm
- Helped attach roof rafter braces
- Started attaching some PV panels
Lunch: 2:30pm-3:30pm
Afternoon: 3:30pm-6:20pm
- Measured out PV spacing on most runners
- Attached front PV mounts on most runners
- Finished installing first row of PV panels
Evening (non-work):
- Spent 2h after work learning/trying out FreeCAD 1.0