Strategy:
- List steps in order of duty – Power Cube to Tractor to CEB press
- Assess capacity required
- Allocate tasks to 6 fabricators and local shop
- List risks and recovery plans
- Assess daily, before and after workday
Shopping List
- Identify Power Beyond Fittings for main valves -
Power Cube Tasks
Shake Down Motor Size
- Start with Power Cube mounting. Measure Power Cube and location of mount
- [2] Cut Mount – 1/4x4 by appropriate measurement
- [2] Drill Mounts – 2 holes on ends each
- Transfer punch mount hole locations for top and bottom mount
- Mark mount hole locations on other side of beams
- Weld Mount eye on bottom of Power Cube
- Weld mount eye on bottom Power Cube Mount
- Mag drill holes in frame -
- Mount Power Cube on Tractor
Build Hydraulic tank
- Grind tanks down to clean
- Clean edges and bungs
- Ream any necessary holes
- Lay out 3 sets on welding table
- Close off bungs with fittings
- Tack everything
- Weld
- Assemble