May Production Plan: Difference between revisions
Jump to navigation
Jump to search
Line 29: | Line 29: | ||
*Move PC with tractor I | *Move PC with tractor I | ||
*Mount Power Cube on Tractor | *Mount Power Cube on Tractor | ||
* | *Connect Hoses | ||
'''Build Hydraulic tanks''' | '''Build Hydraulic tanks''' | ||
Line 52: | Line 52: | ||
'''Prepare | '''Prepare Hydraulic system components''' | ||
*tank | *Mount suction strainer in tank | ||
*Mount fittings up to 3/4" hose barb | |||
*Cut hose to size | |||
'''Weld Mufflers – do 8 more''' | '''Weld Mufflers – do 8 more''' |
Revision as of 14:16, 16 June 2011
Strategy:
- List steps in order of duty – Power Cube to Tractor to CEB press
- Assess capacity required
- Allocate tasks to 6 fabricators and local shop
- List risks and recovery plans
- Assess daily, before and after workday
Shopping List
- Identify Power Beyond Fittings for main valves -
Power Cube Tasks
Shake Down Motor Size
- Start with Power Cube mounting. Measure Power Cube and location of mount
- [2] Cut Mount – 1/4x4 by appropriate measurement
- [2] Drill Mounts – 2 holes on ends each
- Transfer punch mount hole locations for top and bottom mount
- Mark mount hole locations on other side of beams
- Weld Mount eye on bottom of Power Cube
- Weld mount eye on bottom Power Cube Mount
- Mag drill holes in frame -
Test Power Cube
- Move PC with tractor I
- Mount Power Cube on Tractor
- Connect Hoses
Build Hydraulic tanks
- Work on 3 at a time
- Grind tanks down to clean
- Clean edges and bungs
- Ream any necessary holes
- Lay out 3 sets on welding table
- Close off bungs with fittings
- Tack everything
- Weld
- Assemble
Prepare Engine and Pump Mounting
- Assess fittings for hydraulic pump
- Put fittings on hydraulic pump
- Cut plate for Engine Mount
- Cut plate for hydraulic pump
- [1] Cut angle for Power Cube Mount
Prepare Hydraulic system components
- Mount suction strainer in tank
- Mount fittings up to 3/4" hose barb
- Cut hose to size
Weld Mufflers – do 8 more
- Secure 8 close nips, 1”
- Secure 8 elbows, 1”
- Cut 2 rings – flange and end piece of large tube
- Grind and ream rings
- Prepare 1 washer – 1/2” - for closing inner tube
- Prepare 1 closure of washer
- Mark pattern for muffler flange
- Torch muffler flange, use #1 torch head
- Procure gasket material for mufflers
- M
“Prepare Second Generator”
- Put fittings on motor
- Pack up old motor