2011 marks the buildout of Factor e Farm for the purpose of absorbing 12 people full time with comfortable accommodations and work space. We are planning on using the CEB press and strawbale insulation as the core of the built environment. The planned infrastructure buildout includes 6 superinsulated studios, 6 more 3-season studios, common kitchen, common shower/bathroom, electrical power infrastructure, and 3000 square foot workshop addition
2011 marks the buildout of Factor e Farm for the purpose of absorbing 12 people full time with comfortable accommodations and work space. We are planning on using the CEB press and strawbale insulation as the core of the built environment. The planned infrastructure buildout includes 6 superinsulated studios, 6 more 3-season studios, common kitchen, common shower/bathroom, supporting electrical power and internet infrastructure, and a 3000 square foot workshop addition


=Infrastructure Plan=
=Infrastructure Plan=

Revision as of 22:36, 18 June 2011

Introduction

2011 marks the buildout of Factor e Farm for the purpose of absorbing 12 people full time with comfortable accommodations and work space. We are planning on using the CEB press and strawbale insulation as the core of the built environment. The planned infrastructure buildout includes 6 superinsulated studios, 6 more 3-season studios, common kitchen, common shower/bathroom, supporting electrical power and internet infrastructure, and a 3000 square foot workshop addition

Infrastructure Plan

We will allocate $60k to this project as follows:

  • $1k - baler
  • $4k - fully automatic CEB press (2 total)
  • $3.5k -
  • $2k - 20 kW-hr forklift battery bank
  • $1k - 5 kW inverter, 24V
  • $2k -