== Sun Jun 15, 2026 == | |||
=== Meeting Summary === | |||
Jumping in hard on design work. Split into teams to work on different design aspects. The electrical team worked on battery needs and wiring. Mechanical team split into teams working on direction control switch, motor/gearbox housing, and handle/pcb housing. | |||
=== Completed Tasks === | |||
* Ordered remaining electrical parts | |||
=== TODO === | |||
* Continue design work | |||
* Make rapid prototypes (Print! Print! Print!) | |||
=== Related Pages === | |||
* [[Drill Initial Design Research]] | |||
== Sun Jun 8, 2026 == | == Sun Jun 8, 2026 == | ||
Latest revision as of 22:52, 18 March 2026
| ||||||||||||||||||||||||||
Sun Jun 15, 2026
Meeting Summary
Jumping in hard on design work. Split into teams to work on different design aspects. The electrical team worked on battery needs and wiring. Mechanical team split into teams working on direction control switch, motor/gearbox housing, and handle/pcb housing.
Completed Tasks
- Ordered remaining electrical parts
TODO
- Continue design work
- Make rapid prototypes (Print! Print! Print!)
Related Pages
Sun Jun 8, 2026
Meeting Summary
Motor components arrived and were tested on the lab bench.
Completed Tasks
- Research battery and energy constraints
TODO
- Purchase battery and an initial adapter for rapid prototyping
- Design and build a proper adapter later
Related Pages
Sun Mar 1, 2026
Meeting Summary
First meeting with the full team. We researched design constraints and began assembling a **bill of materials** for the prototype.
Completed Tasks
Purchases for:
- Motor ✓
- Trigger ✓
- Gearbox ✓
- Chuck ✓
TODO
- Find and purchase initial parts for testing
- Break into more concrete subteams:
- Mechanical
- Electrical