LifeTrac III/Manufacturing Instructions/Drill: Difference between revisions

From Open Source Ecology
Jump to navigation Jump to search
Line 1: Line 1:
{{LifeTracFab}}
{{LifeTracFab}}
{{LifeTracFab}}


Line 4: Line 6:


[[LifeTrac Fab Drill|'''Drill''']]
[[LifeTrac Fab Drill|'''Drill''']]
:*Hole List
==Hole List==
 
=Frame=
 
As a general rule, all the measurements I have listed here will be more accurate if you mark the centre of each tube and then measure the "holes" from the centre out as opposed to from the ends in, in case some tubes are not cut to the exact lengths.
 
Key - (V) = Vertical. (E,W) = East,West. (N,S) = North South.
 
13/16" drill bit used for 3/4" bolts.
 
*[4] 92"×4"×4" Tubes for base.
**[2] Outer base tubes - 13/16" (V)holes 2" from ends. (V)holes 4" front of centres. (E,W)holes for wheel plates 9" & 13" from ends. (V)holes for hydraulic base plate 13-1/4" & 22-3/4" behind centres, 1-1/4" from outer edges.
**[2] Inner base tubes - (V)holes 2" form ends. (V)hole 4" front of centres. (E,W)holes 6", 9" & 13" from ends & (E,W)holes in centres. (V)holes for hydraulic base plate 13-1/4" & 22-3/4" behind centres, 1-1/4" from inner edges.
 
*[3] 60" Under base tubes.
**(V)holes 2" & 10" from ends.
**(N,S)holes 14" form ends.
 
*[2] 55" Front vertical tubes.
**(E,W)holes 2" form tops & 2", 6" & 9" from bottoms.
**(N,S)holes 6" from tops & 5" from bottoms.
 
*[2] 52" Centre vertical tubes.
**(E,W)holes 2" from tops & 6" from bottoms.
**(N,S)holes 6" from tops & 2" from bottoms.
 
*[2] 59" Rear vertical tubes.
**(E,W)holes 6" from tops & 2", 6" & 9" from bottoms.
**(N,S)holes 2" from tops & 5" from bottoms.
 
*[3] 44" Top (overhead E,W) tubes.
**(V)holes 2" from ends.
**(N,S)holes 6" from ends.
 
*[2] 84" Top (overhead N,S) tubes.
**(E,W)holes 2" from ends & in centres.
**(v)holes 6" from ends & 4" from of centres.
 
 
 
 
==Drill Tool Guides==
:*Magdrill
:*Magdrill
:*Drill
:*Drill

Revision as of 22:44, 13 July 2011

LifeTrac Fab
Prepare - Cut - Drill - Misc - Assemble - Weld - Mount - Finish
LifeTrac Fab
Prepare - Cut - Drill - Misc - Assemble - Weld - Mount - Finish

Sections

Drill

Hole List

Frame

As a general rule, all the measurements I have listed here will be more accurate if you mark the centre of each tube and then measure the "holes" from the centre out as opposed to from the ends in, in case some tubes are not cut to the exact lengths.

Key - (V) = Vertical. (E,W) = East,West. (N,S) = North South.

13/16" drill bit used for 3/4" bolts.

  • [4] 92"×4"×4" Tubes for base.
    • [2] Outer base tubes - 13/16" (V)holes 2" from ends. (V)holes 4" front of centres. (E,W)holes for wheel plates 9" & 13" from ends. (V)holes for hydraulic base plate 13-1/4" & 22-3/4" behind centres, 1-1/4" from outer edges.
    • [2] Inner base tubes - (V)holes 2" form ends. (V)hole 4" front of centres. (E,W)holes 6", 9" & 13" from ends & (E,W)holes in centres. (V)holes for hydraulic base plate 13-1/4" & 22-3/4" behind centres, 1-1/4" from inner edges.
  • [3] 60" Under base tubes.
    • (V)holes 2" & 10" from ends.
    • (N,S)holes 14" form ends.
  • [2] 55" Front vertical tubes.
    • (E,W)holes 2" form tops & 2", 6" & 9" from bottoms.
    • (N,S)holes 6" from tops & 5" from bottoms.
  • [2] 52" Centre vertical tubes.
    • (E,W)holes 2" from tops & 6" from bottoms.
    • (N,S)holes 6" from tops & 2" from bottoms.
  • [2] 59" Rear vertical tubes.
    • (E,W)holes 6" from tops & 2", 6" & 9" from bottoms.
    • (N,S)holes 2" from tops & 5" from bottoms.
  • [3] 44" Top (overhead E,W) tubes.
    • (V)holes 2" from ends.
    • (N,S)holes 6" from ends.
  • [2] 84" Top (overhead N,S) tubes.
    • (E,W)holes 2" from ends & in centres.
    • (v)holes 6" from ends & 4" from of centres.